Construction guarantee call
The applicant, NAD Property Income Fund (Pty) Ltd (“NAD”), by way of application proceedings, sought to enforce payment of a construction guarantee by the first respondent, Guardrisk Insurance Company Limited (“Guardrisk”).[1]
Background
NAD and the third respondent, Belo and Kies Construction (Pty) Ltd (“BK”) concluded a construction contract (in the form of a Joint Building Construction Contract).
Pursuant to such construction contract, BK had a guarantee issued by the second respondent, Performance and Custom Bond Services (Pty) Ltd (“PCBS”), on behalf of Guardrisk (NAD being the beneficiary thereof).
Clause 5 of the guarantee provided as follows:
“Subject to the Guarantor’s maximum liability …, the Guarantor hereby undertakes to pay the Employer the guaranteed Sum or the full outstanding balance upon receipt of a first written demand from the Employer to the Guarantor at the Guarantor’s Physical address calling up this Construction Guarantee stating that:
5.1????????….
5.2????????A provisional sequestration or liquidation order has been granted against the Contractor and the Construction Guarantee is called up in terms of 5.0. The demand shall enclose a copy of the court order.”
Disputes and interim arbitration award
Disputes arose between NAD and BK (which were referred to arbitration). By agreement between NAD and BK, an interim award was published which, in so far as is relevant, read as follows:
“The respondent [NAD] shall not call on the guarantee, issued in terms of the Acornhoek contract concluded between the claimant [BK] and the respondent, until the final determination of all the disputes between … BK and the respondent in respect of the Dwarsloop and Acornhoek projects which are and/or may be placed before Mr Mahon in the pending arbitration (or any other arbitrator, including any appeal proceedings.)”
BK liquidation
On 29 June 2022 BK was liquidated. The third to fifth respondents cited in the application proceedings were its liquidators (who also opposed NAD’s application).
On 4 July 2022 NAD called up the guarantee (relying on clauses 5 and 5.2 of the guarantee above).
Parties’ submissions
NAD submitted that it had met the terms of the guarantee and nothing further needed to be proved. It stated that BK’s final liquidation was a new and self-standing trigger which entitled it to payment from Guardrisk.
Guardrisk’s response was that NAD’s call was in bad faith and opportunistic (as the disputes between BK and NAD were not finally determined). It and PCBS submitted that on a proper interpretation of the interim award, taking into account context and commercial purpose, NAD’s application should be dismissed (as the interim award precluded a call for whatever reasons, including the liquidation of BK, pending the final determination of the arbitration). Accordingly, they submitted that BK’s liquidation was of no consequence.
BK’s liquidators, without referring the court to any authority on this point, contended further that the interim award effectively amended NAD’s rights to call up the guarantee.
The defences raised were as follows:
?
?
?
?
?
Legal principles
The High Court reiterated the following principles:
领英推荐
?
?
?
High Court decision
The High Court rejected the defences raised for the following reasons:
?
?
?
?
?
?
?
It therefore held there was no defence to NAD’s call and ordered Guardrisk to pay R15?179?698,26, and interest from date of NAD’s demand to date of payment.
The respondents were also ordered to pay NAD’s legal costs (jointly and severally).
[1] 029956/2022 Pretoria, High Court (Judgment handed down by Bam J on 5 July 2023)
[2] Citing Lombard Insurance Company Ltd v Landmark Holding (Pty) Ltd and Others 2010 (2) SA 86 (SCA)
[3] Citing Eskom Holdings v Hitachi Power Africa
[4] Citing Coface South Africa Insurance Co Ltd v East London Own Haven t/a Own Haven
[5] Citing Loomcraft Fabrics CC v Nedbank Ltd & Another