A Comprehensive Guide to Prioritizing Projects Using Business Economics

A Comprehensive Guide to Prioritizing Projects Using Business Economics

When resources are limited but opportunities abound, deciding which project to prioritize can be a daunting challenge. Many organizations fall into the trap of subjective decision-making, relying on the opinions of senior executives or group consensus without a structured approach. However, leveraging business economics to evaluate and prioritize projects can transform this process into a strategic, data-driven practice.

Below is an in-depth, step-by-step guide to using economic frameworks for project prioritization, with actionable insights to help you make smarter decisions.


Step 1: Establish a Common Metric for All Decisions

To effectively compare projects, it is crucial to use a single standardized unit of measurement—typically money. Translating every decision into a common metric enables you to objectively weigh the potential costs and benefits of diverse projects.

How to Do It:

  • Identify the total costs associated with each project, including development, maintenance, and opportunity costs.
  • Estimate the potential benefits, such as revenue, cost savings, or market share gains, expressed in monetary terms.
  • Use these figures to calculate a net economic impact for each option.

Example: Imagine you’re considering two projects:

  • Project A: Enhancing website performance at a cost of $50,000, with an expected revenue increase of $200,000 over the next year.
  • Project B: Developing a new software product for $150,000, with potential revenue of $400,000. By calculating the net impact, you can directly compare the projects:
  • Project A: $200,000 - $50,000 = $150,000 net benefit.
  • Project B: $400,000 - $150,000 = $250,000 net benefit.

With these numbers, you have a starting point for your decision.


Step 2: Use Decision Trees to Weigh Risks and Rewards

Decision trees are powerful tools for visualizing potential outcomes, especially when risks and uncertainties are involved. By mapping out possible scenarios and assigning probabilities to each, you can calculate the expected value of a project and make data-informed decisions.

How to Create a Decision Tree:

  1. List Your Options: Define the projects or investments under consideration.
  2. Identify Costs and Outcomes: Determine the costs and potential financial outcomes of success or failure for each option.
  3. Assign Probabilities: Estimate the likelihood of success or failure based on market research, past performance, or expert input.
  4. Calculate the Expected Value (EV): Multiply each potential outcome by its probability, then sum the results to determine the EV for each project.

Example: You’re considering developing two products:

  • Product X: Costs $100,000 with a 70% chance of generating $500,000 in revenue and a 30% chance of earning nothing. Expected Value: (0.7×500,000)+(0.3×0)?100,000=250,000(0.7 \times 500,000) + (0.3 \times 0) - 100,000 = 250,000(0.7×500,000)+(0.3×0)?100,000=250,000
  • Product Y: Costs $50,000 with an 80% chance of generating $300,000 in revenue and a 20% chance of earning nothing. Expected Value: (0.8×300,000)+(0.2×0)?50,000=190,000(0.8 \times 300,000) + (0.2 \times 0) - 50,000 = 190,000(0.8×300,000)+(0.2×0)?50,000=190,000

In this case, Product X has the higher EV, making it the better investment despite its higher cost.


Step 3: Evaluate the Cost of Delay

The cost of delay helps you quantify the economic impact of postponing a project. This framework enables prioritization by highlighting the urgency and opportunity costs of different initiatives.

Scenario 1: Complete Task A First

  1. Task A Costs:3 weeks × $20,000 per week = $60,000
  2. Task B Costs:Delay cost: 3 weeks × $10,000 per week = $30,000Development time: 2 weeks × $10,000 per week = $20,000Total Task B costs = $30,000 (delay) + $20,000 (development) = $50,000
  3. Total Delay Cost: $60,000 (Task A) + $50,000 (Task B) = $110,000

Scenario 2: Complete Task B First

  1. Task B Costs:Delay cost: NoneDevelopment time: 2 weeks × $10,000 per week = $20,000
  2. Task A Costs:Delay cost: 1 week × $20,000 per week = $20,000Development time: 3 weeks × $10,000 per week = $30,000Total Task A costs = $20,000 (delay) + $30,000 (development) = $50,000
  3. Total Delay Cost: $20,000 (Task B) + $50,000 (Task A) = $120,000

Which Task Should You Do First?

  • Completing Task A first results in a total delay cost of $110,000.
  • Completing Task B first results in a higher total delay cost of $120,000.

Conclusion: Prioritize Task A to minimize overall delay costs. This analysis illustrates how considering both direct delay impacts and development timelines can lead to more effective project prioritization.


Step 4: Focus on “Good Enough” Precision

Perfection isn’t required—utility is. Ballpark estimates often suffice for prioritization. Avoid hyper-accuracy, which can waste time and resources without yielding better decisions.


Step 5: Mitigate Risks Through Experiments

Break high-stakes decisions into smaller steps. Use prototypes or small tests to validate assumptions before committing to full-scale implementation.


Step 6: Leverage Optionality for High Upside Opportunities

Diversify efforts for initiatives with significant potential rewards. Expect some to fail, but rely on the successes to offset the losses.


Step 7: Record and Review Assumptions

Documenting assumptions creates transparency and provides a foundation for refining decisions. Regularly revisit them to adapt to new information.


Final Thoughts

Incorporating economic frameworks into project prioritization transforms decision-making into a strategic, collaborative process. Use these methods to ensure your projects align with financial and organizational goals.


?? Your Turn!

  • How do you prioritize projects in your organization?
  • What frameworks or tools have worked for you?

Share your thoughts in the comments, and let’s learn from each other!