Challenges in Proving Prolongation Claims in Construction Contracts
Pragmatic Project Consilium
Counsel of Contract & Claim Specialists for EPC - Oil & Gas Construction Industry
Prolongation claims, a common aspect of construction disputes, arise when a project encounters delays that increase the contractor’s costs. Successfully proving these claims can be challenging, as contractors must demonstrate that the delay was not due to their actions and directly resulted in extended costs. This article covers some of the main challenges in proving prolongation claims and provides insights on how contractors can effectively address them.
1. Limited Understanding of Prolongation Claims Requirements
One of the primary challenges contractors face is fully understanding the specific requirements for a valid prolongation claim. Prolongation claims rely on provisions related to extensions of time (EoT) and compensation for delays under the contract. A lack of understanding of these clauses or the legal framework governing prolongation claims often results in claims being rejected or undervalued.
In the road construction sector, a contractor may assume that all delays are compensable and submit a claim without analyzing the contract’s specific requirements for prolongation claims. In a recent highway expansion project, a contractor’s claim for delay compensation was denied because they failed to demonstrate how the delays fell under the contract’s excusable and compensable delay clauses. Understanding and interpreting contract provisions correctly is essential to avoid similar pitfalls.
2. Difficulty Establishing Direct Causation and Responsibility
Prolongation claims require clear evidence linking the delay directly to the employer’s actions or other parties’ failures. Establishing causation is often complex, especially when multiple factors contribute to delays. Contractors must identify the specific event(s) that caused the delay and show that it was beyond their control, with adequate documentation proving the employer’s responsibility.
In a hospital construction project, delays in receiving government permits extended the completion timeline, leading to cost increases. However, the contractor struggled to prove that the delays were solely the government’s fault, as the employer argued that the contractor’s slow submission of required documents also contributed. Establishing causation in such cases requires precise documentation of all actions, demonstrating that the delay originated from the employer’s side rather than any contractor negligence.
3. Failure to Comply with Timely Notification Requirements
Most construction contracts include notification clauses that require contractors to promptly notify the employer of any potential delays. If contractors fail to provide notice within the specified timeframe, they risk having their claims invalidated. Meeting these notification requirements promptly and accurately is crucial, as it establishes an official record of the delay and preserves the right to claim compensation.
In the railway sector, a contractor on a new track project encountered delays due to unforeseen underground utilities, but they failed to notify the client immediately as per contract requirements. When they later submitted a prolongation claim, it was rejected on the grounds that the notification was delayed, violating contractual terms. This example illustrates the importance of adhering to prompt notification requirements to safeguard the right to claim.
4. Inadequate Documentation of On-Site Conditions
Detailed and consistent record-keeping is essential in supporting prolongation claims. Contractors must provide clear records of daily on-site activities, resources, and any delay-related costs. Without robust documentation, it becomes challenging to demonstrate the impact of delays and the costs incurred. Missing or incomplete records are a frequent reason for rejected or minimized claims.
In a bridge construction project, delays were caused by unexpected geological conditions that increased the time required for foundation work. However, the contractor’s poor documentation of daily conditions and labor hours led to difficulty in proving the exact impact of these conditions on the project timeline. In cases like this, consistent record-keeping can provide the essential evidence needed to support prolongation claims.
5. Difficulty Proving Impact on Critical Path
To establish entitlement for a prolongation claim, contractors must show that the delay affected the project’s critical path. Critical path analysis (CPA) is commonly used to demonstrate how a delay directly impacted the project timeline, pushing the completion date. If the delay cannot be shown to have affected the critical path, it is unlikely to be considered valid for prolongation.
In a residential high-rise development, delays due to supply chain disruptions for essential materials led the contractor to submit a prolongation claim. However, the client’s defense argued that the delays did not impact the critical path, as other tasks could continue unaffected. Without a clear critical path analysis, the contractor struggled to show that these delays directly extended the project’s completion date, highlighting the importance of CPA in prolongation claims.
6. Challenges Distinguishing Between Compensable and Non-Compensable Delays
Construction delays are generally categorized as either compensable or excusable, with only compensable delays entitling contractors to financial compensation. Contractors must clearly differentiate between these types of delays and ensure their claims are only for compensable delays. Misinterpretation or improper categorization often results in claims being rejected or reduced.
On an airport expansion project, the contractor encountered delays caused partly by the employer’s design changes and partly by adverse weather. The contractor sought compensation for both delays, but the employer contested that only the design changes were compensable under the contract. This example shows how understanding the difference between excusable (non-compensable) and compensable delays is crucial to successfully prove a prolongation claim.
7. Accurately Quantifying Prolongation Costs
Prolongation costs include expenses for labor, equipment, site overheads, and head office overheads associated with the delay period. Contractors must accurately calculate these costs, providing clear evidence to support them. Mistakes in cost estimation or lack of documentation can lead to the claim being undervalued or dismissed, so precise quantification is vital.
In a power plant construction project, the contractor’s failure to keep detailed records of extended labor and equipment costs during a delay period led to issues in calculating accurate prolongation costs. When submitting their claim, the contractor’s estimates were questioned, and a significant portion was disallowed due to lack of documented support. This illustrates the importance of recording all additional costs meticulously to avoid claim reduction or dismissal.
8. Handling Issues of Concurrent Delays
Concurrent delays occur when both parties contribute to a delay, making it difficult to assign sole responsibility to one side. To claim compensation for a prolongation delay, contractors must separate concurrent delays and show which portion was attributable to the employer. Proper analysis of concurrent delays can make the difference between a successful and unsuccessful claim.
In a port development project, both the employer’s slow decision-making and the contractor’s labor shortage contributed to project delays. The contractor’s claim for prolongation costs was disputed due to concurrent delays, and without clear analysis distinguishing the delays, the contractor faced challenges in attributing delays solely to the employer. Accurate concurrent delay analysis is essential to avoid having compensable portions of a delay denied.
9. Meeting the Burden of Proof
The contractor carries the burden of proof in a prolongation claim, meaning they must present strong evidence to substantiate each aspect of the claim. This includes project schedules, daily reports, and communications that confirm the cause, impact, and cost of the delay. Failing to meet this burden by lacking clear evidence or incomplete records weakens the claim significantly.
In a water treatment plant construction, the contractor claimed prolongation costs due to delayed permit approvals by local authorities. However, they lacked adequate documentation to demonstrate that the delays directly impacted costs. Without sufficient evidence, their claim was weakened, as they couldn’t conclusively link the delay to additional costs. This example shows that the burden of proof is crucial in demonstrating entitlement to a prolongation claim.
10. Selecting the Appropriate Delay Analysis Method
There are various delay analysis methods that can be used to demonstrate the effect of a delay, including time-impact analysis, as-planned vs. as-built analysis, and windows analysis. Selecting the correct method is crucial, as using an inappropriate analysis technique can lead to inaccurate findings. The method should align with the contract terms, the specific nature of the delay, and the available documentation.
In a wind farm installation project, the contractor attempted to use an “as-planned vs. as-built” delay analysis method, but the employer argued that a “windows analysis” would have been more appropriate given the phased nature of the work. This led to disputes over the accuracy of the delay impact. Selecting the right delay analysis method based on project specifics is essential for presenting a credible claim that accurately represents delay impacts.
11. Navigating Dispute Resolution Procedures
When prolongation claims are contested, the dispute resolution process—whether through mediation, arbitration, or litigation—becomes an important factor. Contractors must be prepared to present a compelling case supported by strong evidence, effective delay analysis, and a clear narrative of events. Familiarity with dispute resolution procedures can improve a contractor’s chances of obtaining compensation.
In a mega mall development project, a contractor’s prolongation claim was rejected, prompting arbitration. The contractor, unprepared for the arbitration process, presented insufficient evidence, weakening their position. This example shows the importance of navigating dispute resolution effectively, with clear evidence and well-prepared arguments. Being well-versed in dispute procedures and prepared for detailed examination can make a significant difference in claim outcomes.
Conclusion
Proving a prolongation claim is often a complicated and demanding task. Contractors must carefully document delays, establish clear causation, quantify costs accurately, and choose appropriate delay analysis methods. Overcoming these challenges requires not only thorough preparation but also a deep understanding of the legal and contractual principles underlying prolongation claims. By addressing these potential obstacles, contractors can improve their chances of obtaining compensation for delays that are beyond their control.
For Inquiries Contact [email protected]
PMP & Six Sigma Green Belt Certified Mechanical Engineer | Expert in Project Management for Oil, Gas, Water & Renewable Energy | Planning/Scheduling Lead | Change Management Specialist | ISO 9001/2015 from CQI / IRCA
2 周Prolongation claim are settled to maintain customers satisfaction and vendor relationship management
FCIARB, FIITARB, FIE, FIV, LLM( Pro), PGD NALSAR , Diploma in Arbitration Practice, MA Mediation, A construction contract and ADR expert
2 周In my experience, most prolongation claims are more wishful than substantiated.
Empaneled Arbitrator ICA,IITArb,CIAC, Kerala and Punjab and Haryana HighCourt, Mediator, conciliator. Techno Legal Consultant. Advocate
2 周Given reasons as to why the prolongation is OK , justification is still ok ! Accounting for proving the impact , needs elaboration as many failed because they could not prove impact on their financial stastics separately for the prolonged contract !! See if you can throw some light on this !!