Casing Drilling Reduces Surface Sections Duration by 50%
Image: 1000 HP Land Drilling Rig.

Casing Drilling Reduces Surface Sections Duration by 50%

Abstract?

This article covers the successful application of non-retrievable casing drilling technology in surface sections.

Background?

No alt text provided for this image
No alt text provided for this image

We experienced total losses, wellbore collapse, and bit balling issues within the first 150 m.

The big (up to 2 in) and poorly consolidated boulders fell on top of our drill-pipe conveyed assemblies and increased the likelihood of getting mechanically stuck. We drilled this interval using thick mud to improve the carrying capacity and low flow rates to avoid washing out the hole.?

No alt text provided for this image

The reactive shale underneath this interval required the opposite approach; the use of thin mud mixed with ecofriendly surfactant and high flow rates. To make matters worse, it was difficult recognizing?when the transition between these two lithologies occurred, which led to bit balling issues and additional trips.

The remainder of the section was composed by interbedded sand and shale layers that did not present any major operational issues.?

Design?

We used computer software for running hydraulics, torque, and drag models, and helping us envision the ideal operation. We fed these using offsets surveys, sliding sheets, drilling logs, and mud checks, among others.

We designed these jobs for using flow rates in excess of 400 gpm and limiting the penetration rate to 50 mph. We anticipated total pressure losses of 800 psi, equivalent circulating densities of 9.7 ppg EMW, and very good hole cleaning indexes. We did not expect buckling or exceeding torque limits during drilling or tripping.

Risks

We implemented multiple safeguards for mitigating risks such as:

  • Casing bit wear
  • Casing bit balling
  • Plugged nozzles
  • Washed out floating equipment
  • Casing and connection failure
  • Casing stuck with big boulders
  • Higher swab and surge pressures
  • Higher equivalent circulating densities
  • Cement slurry flash-setting (nozzles)
  • Next section bit damage during drill-out

Trade-Offs

We traded-off the followings to achieve the objective of reducing the phase time.

  • Casing stand-off reduction
  • No directional surveys
  • No open hole wireline logs

Surface Equipment

The rig did not require any modification.

We made-up a casing running tool to the top drive system to have the capability to rotate and make-up the casing string.?We had a set of link tilt arms with single joint elevators to pick the joints out of the pipe wrangler and stab them onto the string set on slips. We used hydraulic slips to improve both safety and performance efficiency.

We used one rig pump for drilling and the other for jetting the returns out of the cellar hole.

Drilling Assembly

The non-retrievable drilling assembly was entirely conveyed with 9-5/8 in casing.

No alt text provided for this image
No alt text provided for this image

The float valve had a 4-1/4 in diameter valve to ensure the highest possible flow rate capacity, thus minimizing float wash-out events. We used a single non-rotating plug system for cement displacement.

The bit was manufactured with drillable materials and welded to 3 feet long pup joints. It was designed for medium to hard applications to minimize the chances of damaging it within the boulders interval. We minimized the blade count and cutters density to easily drilling-it-out using standard bits.

We did not have deviation issues despite the fact we did not run stabilizers.?

The wellhead bottom pin connection exceeded the well requirements for tension, torque, and pressure, thus easing both make-up and landing operations.

Procedure

We used this procedure on every well:

  1. Performed rig-up
  2. Held pre-spud meeting
  3. Picked-up the casing drilling assembly
  4. Drilled with casing to total depth
  5. Performed the cement job
  6. Installed the wellhead A section
  7. Installed the blowout preventer equipment
  8. Drilled-out the shoe track
  9. Continued with the next phase operations

No alt text provided for this image

Improvements?

The higher annular velocity improved the boulders carrying capacity, the smearing effect built stronger filter cake that avoided both losses and collapses along the boulders interval, and the higher flow rate avoided balling issues and improved the rate of penetration by 40%.

Smearing Effect

We had less and much smaller cuttings, as these were smeared and grinded downhole by the action of the casing pressing them against the wellbore wall multiple times before arriving to the surface. We evidenced the benefits of the smearing effect, thus reducing mud, solids control, cement, and logistics costs.

No alt text provided for this image

Well Control

We did not take any kick.?We only used the water based mud hydrostatic for well control purposes as there was no blowout preventer equipment installed.

We exercised higher well control awareness as we had smaller annular clearances than when running drill-pipe assisted assemblies. We trained drillers on correct connection practices to minimize swab and surge pressures.

Results

The implementation of the non-retrievable technology for drilling surface sections quickly ended-up being economical.?We drilled dozens of wells, reducing the phase time by 50% and breaking-even the additional expenses with time savings.


Get in touch at [email protected] if you would like to discuss in detail the value I can add to your team.

Glad to see someone utilizing this technology for surface holes. I drilled 4 1/2" casing to 8000' in the Anadarko basin using a PDC casing bit. No one thought it would last.

Mark Jayne

Support Technician (On Long Term sick leave), ex-Mud logging Instructor

2 年

Max - Well written and thought out and shows as much preparation and planning has been done that would be exercised for a HPHT type well. With so many well issues certainly keeps the crews on their toes and shows the tale of ''the tortoise and the hare race'' is very apt for this sort of well.

Antonio Florez

General Manager at Grupo Sierra Alta

2 年

Agree with S. Rosenberg comment.

Rudy Harsanto

IWCF Level 4 Combined Surface & Subsea BOP Certified Drilling Supervisor, Drilling Superintendent

2 年

And still need to be more challenging on supervising on rig floor, particularly for technical aspect to deal with contingency plan ahead, especially for the CWD retrievable BHA type, not to get the surface casing stuck when about washing over the casing & covering up the rest of BHA below the casing toward its final setting depth.

Virgoes Wijaya

Drilling Supervisor

2 年

Thanks for posting

要查看或添加评论,请登录

社区洞察

其他会员也浏览了