The hydropower plant is located in southern Norway and has a drop of 20 meters. The total installed capacity is 208 MW and the annual generation is 900 GWh.

Challenge

To secure a controlled water flow, the sluice gates at the power station need to handle intake and spill water at any time, even in case of power interruption to the motors.

During an upgrade of the power station, the old DC motors for the sluice gates were replaced.

Ingen alternativ text angiven f?r den h?r bilden

Solution

To ensure the emergency operation of the AC motors, UMD? system secures operation of the AC-motor from both the mains and battery supply.

Ingen alternativ text angiven f?r den h?r bilden

Uninterruptible Motor Drive

UMD? is the most reliable way to power your motor and secure the operation of a standard AC-motor. The UMD will be backed up by existing batteries on site and thereby replace the old DC motor solution.

The transition from mains supply to battery supply is automatic and seamless

Ingen alternativ text angiven f?r den h?r bilden

Benefits

  • Standardized, Type Tested Systems
  • Highest Possible Availability
  • Eliminates Single Point of Failure





“KraftPowercon has decades of experience and we meet high expectations and demands within the industry. In this case we replaced the old DC-motors and provided an Uninterruptible Motor Drive solution for standard three phase AC-motors.”

H?kan Rydenborg - Technical Sales Manager, KraftPowercon

Ingen alternativ text angiven f?r den h?r bilden
Arvid M?rtensson

Technical Sales Developer at KraftPowercon

2 年

Looks very good, well done!

要查看或添加评论,请登录

KraftPowercon Integrated Power Solutions的更多文章

社区洞察

其他会员也浏览了