Case Study - Mitigating the impact of Electrical Hardware Substitution on overall project execution amid TAR timeline pressure
INTECH Automation & Intelligence
Automation & Digital Solutions for Industrial Enterprises
Project Brief
Project Name: Enhancing MCCs Load Capacity for Steam Turbine Fan Motors: INTECH’s Turnkey Solution for Oil & Gas Turnaround Project
Location: West Africa
Industry: Oil & Gas Upstream
Facility: GTL facility in West Africa that began first production in 2014 and is an integral part of the client’s gas use strategy which includes natural gas sales as well as sales of GTL products.
Customer's Question
As part of a major turnaround for 2024, the end user, a major global oil & gas company, planned to increase the output of steam turbines at its facility by replacing a total of 16 ACC fan motors, 200 HP each, with new 250 HP motors, driven by VSD and sofstarter. The end-user required a turnkey solution to upgrade the existing MCCs for supporting the enhanced load.
Urgent Timelines
Since this project was part of a TAR, timelines were critical as the end-user would have faced a daily loss of 1.5 to 1.8 million USD in case of any delays.
Scope
Provision of new type-tested MCCs, Electrical infrastructure upgrade, Current transformer upgrade, End-to-end project management.
Benefits Delivered
Detailed Scope of Work
INTECH’s scope of work included:
Provision of new type-tested MCCs: New Type-tested MCCs from Rockwell Automation Centerline 2100 Series (2500 Amperes Bus rating) with 6 VSDs and 10 Softstarters, suitable for end-user process requirements.
Electrical infrastructure upgrade: Replacement of the existing 2000-ampere busduct with a higher-capacity 2500-ampere busduct. Later, this was replaced with a power cable solution along with cable trays and cable termination boxes.
Current transformer upgrade: Replacement of current transformers within the existing switchgear from 2000/5 amperes to higher-capacity 2500/5 amperes.
End-to-end project management: End-to-end EPC&C services that aligned with customer goals and industry best practices to ensure smooth project execution from design to commissioning.
Project Execution
Phase 1 – Site Survey & Planning
In the initial phases of the project, INTECH conducted a thorough site survey to get insights into existing infrastructure and space availability. This enabled INTECH’s team to understand the area layout, evaluate the condition of the current MCCs, and develop a methodic approach for their dismantlement and replacement with new units.
Phase 2 – Design & Procurement Challenges & Solutions
Challenges
1. Unavailability of the Required Rockwell Automation Type-Tested Main Incoming Unit: INTECH identified that the OEM did not have the main incoming unit of same specs that was type tested. This was the foremost challenge faced during the project’s initial stages, which impacted all the subsequent phases of the project.
领英推荐
2. Replacement of Busducts with Power Cables Implementation of an alternative lower rating unit required the replacement of busducts with power cables to effectively manage short-circuit current flow from the main switchgear to the MCCs. INTECH suggested a minimum cable length of 20 meters for each MCC to limit the short-circuit current. However, this shift in approach posed complexities related to cable routing due to the substation’s low height and congested network of cable trays.
Solutions
1.? Lower Rating Unit to save 4-6 weeks of time & costs Since OEM intimated that they needed an additional 4 to 6 weeks to conduct the required type tests, INTECH, in consultation with the client, utilized a lower rating unit to mitigate delays. While this decision had a far reaching impact, as mentioned, INTECH was able to avoid overruns while also demonstrating exceptional flexibility & execution skill to overcome the challenges that emerged subsequently.
2. 3D Model of E-House for Optimal Cable Routing: To address the problem of cable routing, necessitated by the replacement of busducts, INTECH’s team leveraged its in-house expertise to create a 3D model of the E-House using 2D drawings provided by the client and data collected from the site. This 3D model enabled visualization and analysis of different possible routes that could accommodate the required power cables effectively. Through detailed modeling and analysis, the team developed a plan that met the client’s requirements while ensuring optimal functionality and safety. This proactive approach addressed the immediate issue of accommodating the power cables and showcased INTECH’s commitment to get the job done and adaptability to respond to changing demands & circumstances.
Phase 3 – On-site challenges & solutions
Challenges
1. Space limitations within the station: INTECH faced multiple challenges during this phase, primarily due to the limited area within the substation and, as mentioned, congested network of cable trays while prioritizing the need for effective handling of materials. The limited space required a thorough rigging plan to upgrade MCCs.
2. Maneuverability issue with 3-Core Cables: Responding the client’s request for utilizing 3-core cables within switchgear and MCC areas, the team faced issues related to the bending radii of the cables at the corners and maneuverability inside the switchgear and MCC.
3. SIMOPS related Personnel & Equipment safety concerns: Due to SIMOPS, the area was cluttered with different teams while multiple independent operations caused safety concerns for personnel & equipment.
Solutions
1. Comprehensive Rigging Plan: INTECH successfully addressed challenges posed by limited space through a carefully thought out plan for the dismantling of existing MCCs, their safe movement outside the substation, their rigging, the rigging plan for new MCCs, their movement inside the substation, and their installation.
2. Utilization of Single-Core Unarmored Cables: INTECH’s team proposed the use of single-core unarmored cables in trefoil formation to effectively reduce bending radii and improve maneuverability in switchgear and MCC.
3. INTECH taking responsibility for safety supervision INTECH’s team, along with fulfilling their own responsibilities, also supervised the safety aspect of the SIMOPS, in close coordination with the end user team. The project was closed out with zero incidents of injury or equipment damage.
Phase 4 – Commissioning challenges & solutions
Challenges
1. Switchgear Bus Risers ampacity: INTECH timely notified the end-user team regarding the ampacity of switchgear bus risers that required assessment and coordination with the OEM to rectify any discrepancies.
2. Motor VSD & Softstarter issue: During commissioning, abnormal behavior was observed on the VSD and Softstarter in the initial run of few motors. This required a detailed assessment of client-performed terminations on the motor side.
Solutions
1. Collaboration with the client and OEM: INTECH supported the end-user in coordination with the OEM to assess the ampacity of switchgear bus risers and implement necessary resolutions.
2. Root Cause identified and corrections implemented INTECH timely identified the root cause and requested the client to share the terminations details which their team had performed at the motor side. INTECH found an error in the field terminations and proposed a correct method of termination based on OEM documents. After helping the client team with implementing corrections, the commissioning progressed smoothly.
INTECH’s continued support
INTECH fulfilled its scope of work and was able to deliver the turnkey solution as per the agreed timelines. In addition, INTECH kept its resources engaged on-site for an extended length of time to provide support in related activities that were peripheral to INTECH’s scope. Utilizing its network, INTECH was also able to help the client with logistics arrangements and mobilization of backup resources.
?
Electrical Engineer | Project Management | Design & Engineering | Maintenance | Reliability
2 个月Osama Idris great work!
Instrumentation, Cyber Security, Automation, Control System, Functional Safety, Maintenance, Projects, Engineering, Oil & Gas, LNG, LPG, OT
2 个月Atiq ur Rehman
Projects & Engineering l X PepsiCo | X Akzonobel Project l X Packages & Bulleh Shah l Supply chain | Plant Maintenance & Operations
2 个月Excellent
xINTECH | xJaffer | Seasoned Planning Engineer | PMO Analyst | Power BI | MSP & P6 Expert |
2 个月Osama Idris
Project Management Professional | Engineering Management Professional
2 个月This is truly an impressive case study showcasing INTECH’s adaptability and expertise under critical TAR timeline pressures! The ability to pivot with alternative solutions, like utilizing lower-rating units and deploying single-core unarmored cables, demonstrates not only technical excellence but also a strong commitment to meeting client objectives without compromising safety or efficiency. The use of a 3D model for optimal cable routing is a standout approach, highlighting innovative problem-solving in a challenging environment. Kudos to the INTECH team for delivering a zero-incident project and providing extended support beyond the original scope—truly a hallmark of reliability and professionalism in the oil and gas industry!