Case Study – How Proactive Electrical Maintenance team saved a Power Transformer
Avinash Singh
38000+ Connections, Consulting, Manager (Electrical Services and Consulting)
Hello Connections,
Your valuable 10 minutes may avoid breakdown of Electrical Equipment in your plant
Today, we are going to present a case study of ‘POWER TRANSFORMER’, which we never heard off or thought that such even case may happen in plants but happened in one. However, we wish to share the experience, so that the problem Maintenance Engineers faced in that plant, may not be faced by others or can be avoided.
This case study shows, how Pro-active Engineers, preventive Maintenance & Routine testing activities can save your Electrical Equipments and Revenue worth crores.
Power transformer of rating 31.5 MVA, 66/11 kV is used for power distribution to utilities through an 11 kV switch-gear, they were having three Transformers of identical rating, in which all three transformers are in charged condition & the transformer which we are talking about is used as a standby transformer.
The transformers were in charged condition, predominantly the 1st and 3rd transformers were in a loaded condition comparative with the 2nd one. Almost one year passed, all three transformers were functioning normally, with a load of 10 to 20% of its rated capacity.
Incident of Fault :
As a yearly Preventive maintenance activity, the all 3 transformers maintenance has been carried out, everything was found in order, the mineral oil samples of all three transformers were collected and has been sent to the nearest Lab for analysis of DGA, BDV & water content.
The DGA test results of Transformer#2 was found abnormal compared with the past test results (first result before charging), the C2H4(Ethylene) content was found immense, as per IEEE C57.104 standards it should be less than 50 ppm. But where has in the test result, the content of C2H4 was found around 402 ppm, almost 8 times the specified limit as per IEEE.
The Maintenance team didn’t take any final verdict on shutting down the transformer, for more assurance, they have sent the oil samples to another four labs just for checking the actual increase in C2H4 by authenticating with their own lab results, the samples were sent to two private labs, one to OEM and one sample to ERDA, all the results were not the same, moreover there is a significant change in C2H4 as compared with others.
Below is the results of Oil test : -
COMPARISON OF DGA RESULTS
The Transformer is de-energized & OEM representative has been called out to the plant location to further scrutinize the case, the site team performed some electrical tests to ensure the healthiness, the test results were found in order.
The oil has been drained out of the transformer, the manhole covers were removed, the core yoke and tank shorting point disconnected/separated, IR test conducted between the separated points (Core & yoke frame) with respect to ground, a voltage of 2500 Volts is applied to check the healthiness of insulation.
As there is a complication to enter inside the transformer due to the space concern between the body and the core-coil assembly, the inspection window in three sides was opened for conducting the above test.
While conducting Insulation resistance test the voltage is notwithstanding/ building up normally, all of a sudden, the team noticed some chattering sound from inside the transformer, all the team members were inspecting the transformer from all three sides of inspection window, but the chattering sound/ spark is not accurately visible.
OEM recommended dispatching the transformer to their works for further investigation, the transformer is dispatched from the site and the site team also reached to OEM works for inspection.
CCA OF THE SAID TRANSFORMER
The core has been lifted from the body and visual inspection performed, no abnormalities found, Insulation resistance between core & yoke frame conducted @ 2500 volts, chattering sound observed.
Finally, case was concluded, one washer found resting on the bottom of a center limb of core and touching the yoke frame resulting in sparking/chattering.
Pic of the washer which was resting in the bottom of the center limb.
OMG! From where this washer came inside the transformer?
We can't judge this now, however, this washer may have gone inside the transformer in OEM workplace itself or else in site during installation of the transformer, we may say that it was sheer negligence or poor workmanship. But this can happen
After removal of washer Insulation resistance test conducted the values were found more than 500 Mega-ohms.
The transformer has been packed and testing has been done, everything found normal, the same has been commissioned and taken in service.
Conclusion that can be drawn from this Incident :
Conclusion which maintenance team of that plant came up with, which may not be feasible, but if they have done it, they could have saved lot of time and money.
Below is the conclusion drawn by the maintenance team of that plant are as below
Points to be considered before & after commissioning of the Transformer (related to this case study) :-
1. After receipt of the transformer at your premises, don’t forget to check the insulation resistance of Core & Yoke frames earthing point individually with respect to the ground/ body.
2. If these points are not available outside the transformer body, then the manhole cover to be removed and all these three points to be isolated and insulation resistance to be conducted as stated in point no 1.
3. DGA to be carried out before charging, after charging (no load 24hrs), in a loaded condition (after 24 hrs) & after a month, where online DGA is not available.
4. DGA / Oil test report should be cross verified (if the report is not within prescribed limits) with a minimum of One NABL accredited labs, before concluding.
5. While erecting transformer and its accessories, one should be very cautious of handling materials and one must double check that nothing is fell inside the transformer tank, before boxing up & oil filtration/ charging.
Hope it will help you, also share this with other Electrical Engineers you know.
Any other suggestions are welcomed.
Regards
Avinash Singh
Group Lead - Electrical Equipment at Reliance Industries Limited
10 个月Thanks Avinash for this wonderful case study. Hope this will be an eye opener for all of us who are not stressing upon measurement of core resistance at the FAT itself. One observation is that the report talks about taking DGA before charging. This I think needs to be thought of as the same might not be that much useful. But definitely, first no load charging and subsequent charging on load will help us set the reference values. The results can be further analysed through appropriate Duval's triangle and pentagons.
Principal Plant Engineer
4 年Thanks a lot engr. Avinash Singh for sharing such case. - C2h2 is also high, and indicates abnormal result. - When you inspected the Tr. Did you check the Tap changer ? If yes how did you find it ?. - The lab results carry a lot of variation which make it difficult to follow up with DGA tests, how you will relay on such results. With best regards,,,
Specialist, Power Transformers
4 年The concluding part seems not complete. When such an incident happens, users must demand from OEM a detailed explanation and get yourself convinced. Must demand the photo showing exactly the positioning of this washer in the core coil assembly. The problem may not be due to bridging of yoke and core by the metallic washer. In service this is anyway shorted. Of course there is a chance for circulating current due to double earthing, depending on the positioning of washer. Checking IR of core and yoke insulation is a routine procedure before starting testing at factory, before starting erection ( some users are so fussy that they will allow unloading of transformer from trailer only after conducting this test ! To ensure no damage during transit) and before commissioning. I do not suspect much sparking; if so acetylene content would have been much more. Large quantity of ethylene means red hot metal more than 500 C. Did the washer had signs of overheating? If the washer was lying near to the leakage flux coming out of HV- LV windings and the flux was hitting on the flat side of washer and it can get red hot at full load.Circulating current, if any, cannot be significant as it is a MV medium power transformer- prc
QA/QC LAB TECHNICIAN at Winchem Middle East Chemical Industries LLC
4 年Good Morning Sir
Specialist, Power Transformers
4 年Leaving sundry items inside transformer and then be detected by user after several years of service is not rare in the history of transformers. It can be fasteners, coins, insulation parts and some times quite embarrassing items like tea kettle, sitting stool, spanners etc,etc (self witness) Transformer manufacturers have introduced several preventive protocols and such issues are rare nowadays. As long as these metallic parts are away from core and coil assembly nothing will happen and the show will go on as transformers passed all tests with these unwanted items.in place. Much more dangerous is metallic parts falling during installation work or loosening out in service due to vibrations and settling in core-coil assembly leading to failure.