Case Study Highlight: First-Time Composite User Finds Success with Flexpipe
In March 2023, a first-time Flexpipe user was able to tie in production faster, with a smaller environmental footprint.
N7 Energy require a pipeline that would not only meet their specific needs and application, but that would also be cost-effective and easy-to-install. After considering alternatives such as steel and fiberglass products, they turned to composite pipe and Flexpipe for the first time.
N7 Energy was looking for a durable, corrosion-resistant option that could handle their emulsion fluid efficiently and that could be seamlessly integrated into their overall pipeline system. By selecting Flexpipe, N7 Energy found an ideal solution that aligned with their requirements.
As Russell Gonie, their Vice President of Operations stated, "The overall Flexpipe experience was great. The people from sales, and project coordinating to field technicians" making the overall project a successful collaboration.
PRODUCT FIT FOR N7 ENERGY'S NEEDS
COST-EFFECTIVE SOLUTIONS
CORROSION-RESISTANCE
DEDICATED FLEXPIPE TEAM
领英推荐
Location: Meekwap, Central Alberta, Canada
Application: Emulsion
Installation Method: Plowing
Products: 4,200 meters (13,779 feet) of 6" FP601 HT and 2,550 meters (8,366 feet) of 3" FP301 HT
Operating Conditions: 300 psi, 75°C (2,000 kPa, 167°F)
Length: 6 days
Date: March 2023
Read more of our success stories: https://bit.ly/3PDcpZv