CAPM Practice Exam Question

CAPM Practice Exam Question

You are part of a project team for a new software development project. The team has just completed the first sprint, but the product owner is not satisfied with the increment because it does not meet their expectations. What should the team do NEXT?

A) Continue with the planned sprints and make adjustments to the product backlog items for future sprints based on the product owner's feedback.

B) Disregard the product owner's feedback for now and proceed with the next sprint as planned, revisiting the feedback after a few more sprints.

C) Suggest that the product owner adjusts their expectations to align with the team's understanding of the project scope and capabilities.

D) Review the sprint with the product owner during the sprint review meeting to understand their concerns, then adapt the product backlog as necessary based on the feedback.


Looking for more practice exam questions like this? Enroll in our online CAPM Exam Prep course , featuring more than 1,700 practice questions. By doing so, you can supercharge your CAPM Exam preparation and earn 37 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!


Best Answer: D) Review the sprint with the product owner during the sprint review meeting to understand their concerns, then adapt the product backlog as necessary based on the feedback.

Explanation:

Based on the information given in the question, we understand that this team is using Scrum. Scrum is an agile framework that values collaboration, customer feedback, and the ability to adapt quickly. The sprint review meeting is a critical ceremony designed for the team to present the increment to stakeholders, including the product owner, and gather feedback. This process ensures that the product being developed aligns closely with the product owner's expectations and the needs of the end-users.

The key principle of Scrum involves inspecting and adapting. By reviewing the sprint outcomes with the product owner and understanding their concerns, the team can make informed decisions about necessary adjustments to the product backlog. This ensures that the work in upcoming sprints is more closely aligned with what is most valuable to the project stakeholders.

The approach of actively seeking to understand and address the product owner's concerns demonstrates the team's commitment to stakeholder satisfaction. It acknowledges the product owner's role as the voice of the customer and ensures that the product developed meets the project's goals and customer needs.

Why Other Options Are Not the Best:

  • Option A (Continue with planned sprints): While this option does involve making adjustments based on feedback, it suggests waiting until future sprints to do so. This delay in addressing feedback can lead to a product that diverges significantly from the product owner's expectations, potentially wasting time and resources.
  • Option B (Disregard the product owner's feedback): Ignoring the product owner's feedback contradicts the core principles of Scrum, which prioritize stakeholder engagement and responsiveness to change. This approach can lead to dissatisfaction and a final product that does not meet the needs of the users or stakeholders.
  • Option C (Suggest adjusting expectations): Asking the product owner to adjust their expectations without first trying to understand and incorporate their feedback can lead to a breakdown in communication and trust between the team and the product owner. It fails to acknowledge the collaborative nature of Scrum and the importance of delivering value.

In summary, Option D is the best choice because it aligns with the Scrum values of collaboration, stakeholder engagement, and adaptability. It ensures that the project benefits from continuous feedback, leading to a product that meets or exceeds the product owner's expectations and provides value to the users.