CAPM Practice Exam Question
You are a project manager and you are reviewing the earned value data for your project. You find that the Planned Value (PV) is $50,000, and the Earned Value (EV) is $48,000. What is the Schedule Variance (SV) of the project?
A) -$2,000
B) $2,000
C) $48,000
D) $50,000
Looking for more practice exam questions like this? Enroll in our online CAPM Exam Prep course featuring approximately 1,700 practice questions. By doing so, you can supercharge your CAPM Exam preparation and earn 37 Contact Hours, essential for your exam application. Enroll now for the ultimate exam readiness!
The Best Answer is A.
Here is a detailed Explanation
Conceptual Understanding:
In this question, you are given:
Using the formula for Schedule Variance (SV):
SV=EV?PV
SV = $48,000 - $50,000
SV = -$2,000
Therefore, the Schedule Variance (SV) is -$2,000, which means the project is behind schedule by $2,000.
Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New
1 年Answer is A