CAPM Practice Exam Question

CAPM Practice Exam Question

You are a project manager and you are reviewing the earned value data for your project. You find that the Planned Value (PV) is $50,000, and the Earned Value (EV) is $48,000. What is the Schedule Variance (SV) of the project?

A) -$2,000

B) $2,000

C) $48,000

D) $50,000


Looking for more practice exam questions like this? Enroll in our online CAPM Exam Prep course featuring approximately 1,700 practice questions. By doing so, you can supercharge your CAPM Exam preparation and earn 37 Contact Hours, essential for your exam application. Enroll now for the ultimate exam readiness!


The Best Answer is A.

Here is a detailed Explanation

Conceptual Understanding:

  • Earned Value Management (EVM) is a technique used to assess the project's performance by comparing what was planned to be done against what has actually been done.
  • Planned Value (PV) is the value of the work that was planned to be completed by a specific time.
  • Earned Value (EV) is the value of the work that has actually been completed by a specific time.
  • Schedule Variance (SV) is calculated as follows: SV=EV?PV
  • Schedule Variance tells us whether we are ahead or behind schedule. A positive SV indicates that we are ahead of schedule, while a negative SV means we are behind schedule.

In this question, you are given:

  • Planned Value (PV) = $50,000
  • Earned Value (EV) = $48,000

Using the formula for Schedule Variance (SV):

SV=EV?PV

SV = $48,000 - $50,000

SV = -$2,000

Therefore, the Schedule Variance (SV) is -$2,000, which means the project is behind schedule by $2,000.

Bungsu Sinabutar

Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New

1 年

Answer is A

回复

要查看或添加评论,请登录

Sabri C.的更多文章

  • PMP Practice Exam Question

    PMP Practice Exam Question

    In a project, the team identifies a risk that a critical feature may not be fully developed within the sprint due to…

    7 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the planning phase of a project, you identify a potential risk of a critical supplier failing to deliver on…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are in the process of closing a project and have received feedback from key stakeholders that certain deliverables…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a team meeting, a conflict arises between two team members, and one of them becomes visibly upset and starts…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the initial stages of a project, your team agrees on a set of ground rules to guide behavior and communication…

    1 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    As a project manager practicing servant leadership, how would you handle a situation where a team member is struggling…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are leading a newly formed project team and notice that team members are unsure about their roles and how their…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a project status meeting, two key team members begin arguing about the best approach to complete a task. Their…

    3 条评论
  • Agile Projects: Redefining How We Build the Future

    Agile Projects: Redefining How We Build the Future

    In a world where change reigns supreme, Agile project management emerges as a transformative approach that embraces…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    During a project, the team completes a sprint and delivers a potentially shippable product increment. However, the…

    2 条评论

社区洞察

其他会员也浏览了