CAPM Practice Exam Question
You are a project manager overseeing the development of a new software application. During the requirement gathering phase, you notice a significant gap between the business goals and the technical team's understanding of these goals. What is the BEST approach to ensure alignment between the business goals and the requirements gathered?
A) Update the project scope document to reflect a change in business goals.
B) Conduct a joint workshop involving both business stakeholders and the technical team.
C) Send an email to all stakeholders summarizing the business goals.
D) Request the business analyst to prepare a detailed report on the business goals.
Looking for more practice exam questions like this? Enroll in our online CAPM Exam Prep course , featuring more than 1,700 practice questions. By doing so, you can supercharge your CAPM Exam preparation and earn 37 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!
领英推荐
Correct Answer: B) Conduct a joint workshop involving both business stakeholders and the technical team.
Explanation:
The correct answer is B, conducting a joint workshop involving both business stakeholders and the technical team. This approach is optimal for ensuring that there is clear and shared understanding among all parties involved. Here's why this is the best course of action:
Option A (updating the project scope document) might be necessary later but doesn’t facilitate mutual understanding. Option C (sending an email) can result in misinterpretations or lack of engagement, and Option D (preparing a detailed report) might not address the immediate need for interaction and clarification. Therefore, conducting a workshop (Option B) is the most effective way to ensure alignment between business goals and technical requirements.