You are managing a construction project. The project is complex with many interconnected activities. You are in the process of creating the project schedule and are determining the sequence of activities.
What is the best tool or technique to use in this scenario to sequence the activities effectively?
A) Work Breakdown Structure (WBS)
B) Critical Path Method (CPM)
C) Gantt Chart
D) Stakeholder Analysis
Looking for more practice exam questions like this? Enroll in our online CAPM Exam Prep course, featuring more than 1,700 practice questions. By doing so, you can supercharge your CAPM Exam preparation and earn 37 Contact Hours, essential for your exam application. Enroll now for the ultimate exam readiness!
领英推荐
Best Answer: B) Critical Path Method (CPM)
Explanation:
CPM is specifically designed for projects where activities and their durations are known and fixed, typical of predictive plan-based methodologies. It allows for precise planning and scheduling.
In complex projects like construction, where activities are interconnected, CPM excels in mapping out dependencies and identifying the sequence that determines the project's minimum duration.
The critical path is the sequence of activities that cannot be delayed without delaying the project. CPM focuses on this aspect, making it invaluable for project managers to prioritize tasks and allocate resources.
By identifying the critical path, CPM also aids in risk management, highlighting areas where delays could have the most significant impact and where contingency plans are most needed.
Why Other Options Are Not the Best:
In conclusion, for a scenario that demands effective sequencing of project activities, especially in complex and interconnected projects like construction, CPM stands out for its ability to identify the critical path, manage project duration, and assist in risk management. The other tools, while important in project management, do not specifically address the sequencing of activities as directly or effectively as CPM does in the context of predictive plan-based methodologies.
Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New
1 年Answer is A
Formateur PMI-ATP PMP-ACP-CAPM/SAFe6 SPC(SA-SSM-POPM-RTE-SP-LPM-DEVOPS) /ISTQB Fdtion V4-Test Manager /PSM I II -PSPO I-icSM-icPO-icSTD /PRINCE2 V7 Accrédité /ITIL 4 Fondation Accrédité- ITIL CDS -ITIL DPI/DEVOPS Fdation
1 年B.CPM Wbs r?le: hiérarchical présentation not sequencing activités. Thé lowest level wbs is work packages.( Not activités)