CAPM Practice Exam Question
A project manager is reviewing the project schedule and notes several tasks that are running concurrently but should have been sequenced. What tool or technique should the project manager use to adjust the dependencies between these tasks?
A) Fast tracking
B) Resource leveling
C) Critical Path Method
D) Precedence Diagramming Method (PDM)
Looking for more practice exam questions like this? Enroll in our online CAPM Exam Prep course, featuring more than 1,700 practice questions. By doing so, you can supercharge your CAPM Exam preparation and earn 37 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!
领英推荐
Best Answer: D) Precedence Diagramming Method (PDM)
Explanation:
The Precedence Diagramming Method (PDM) is the appropriate tool for adjusting and defining task dependencies within a project schedule. This method helps in establishing the correct sequence of tasks by identifying logical relationships and dependencies among them. PDM is a key technique used in the development of a project schedule and is essential for creating a network diagram that visually represents task sequences.
Using the Precedence Diagramming Method, the project manager can rectify the sequencing errors observed in the project schedule, ensuring that all tasks are correctly aligned according to their logical dependencies. This will lead to a more efficient and effective project execution phase.