Your software development team is new to Agile and has just completed their first sprint. During the review, the client suggests several modifications to the features that have been developed. Some team members express concerns that accommodating these changes might impact the project's planned schedule. As a project manager familiar with Agile principles, how should you guide your team to manage these requests effectively without compromising the project’s progress?

A) Educate the team on the Agile principle of welcoming changing requirements, even late in development.

B) Instruct the team to complete the project as initially planned and consider the client's feedback for future projects.

C) Recommend documenting the client's feedback but continuing with the current sprint's goals without alterations.

D) Suggest a hybrid approach where only minor client feedback is integrated into the current sprint.

Looking for more practice exam questions like this? Enroll in our online CAPM Exam Prep course, featuring more than 1,700 practice questions. By doing so, you can supercharge your CAPM Exam preparation and earn 37 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!


Best Answer: A) Educate the team on the Agile principle of welcoming changing requirements, even late in development.

Explanation: In Agile project management, one of the core principles is to embrace changes, even late in the development process, if they provide the customer with a competitive advantage. Addressing the concerns involves several educational and practical steps:

  1. Agile Education: Reinforce the understanding of Agile methodologies, particularly the principle that Agile is designed to be flexible and responsive. This includes educating the team on how changes can be efficiently incorporated into the development process without derailing the project.
  2. Client Collaboration: Emphasize the importance of regular and ongoing collaboration with the client. Agile projects succeed through partnership, and client involvement is crucial. Feedback should be seen as an opportunity to deliver a product that better meets the client's needs.
  3. Backlog Prioritization: Guide the team on how to integrate the client's feedback into the product backlog. This involves evaluating the impact and value of each change request and reprioritizing the backlog items accordingly. This prioritization should be a collaborative effort involving both the development team and the client, ensuring that everyone agrees on what is most important.
  4. Sprint Planning: Teach the team how to adapt their sprint plans to accommodate changes. This includes determining the capacity for new work in each sprint and using sprint planning to discuss how best to implement high-priority changes without significantly affecting the project timeline.
  5. Risk Management and Communication: Address concerns about timeline impacts by developing a clear communication plan that includes setting realistic expectations with the client about the implications of changes on delivery timelines. Use Agile artifacts like burndown charts and velocity tracking to manage and communicate progress and impacts transparently.
  6. Continuous Improvement: Encourage the team to view the Agile transition as a learning process. Each sprint review and retrospective provides opportunities to learn and improve how the team manages changes and incorporates feedback.

By focusing on these aspects, you can help your team understand that Agile is not just about adhering to a new set of processes, but about adopting a mindset that values flexibility, collaboration, and ongoing improvement. This will ultimately lead to better project outcomes and higher client satisfaction.


Bungsu Sinabutar

Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New

8 个月

Answer is A

要查看或添加评论,请登录

Sabri C.的更多文章

  • PMP Practice Exam Question

    PMP Practice Exam Question

    In a project, the team identifies a risk that a critical feature may not be fully developed within the sprint due to…

    7 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the planning phase of a project, you identify a potential risk of a critical supplier failing to deliver on…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are in the process of closing a project and have received feedback from key stakeholders that certain deliverables…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a team meeting, a conflict arises between two team members, and one of them becomes visibly upset and starts…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the initial stages of a project, your team agrees on a set of ground rules to guide behavior and communication…

    1 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    As a project manager practicing servant leadership, how would you handle a situation where a team member is struggling…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are leading a newly formed project team and notice that team members are unsure about their roles and how their…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a project status meeting, two key team members begin arguing about the best approach to complete a task. Their…

    3 条评论
  • Agile Projects: Redefining How We Build the Future

    Agile Projects: Redefining How We Build the Future

    In a world where change reigns supreme, Agile project management emerges as a transformative approach that embraces…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    During a project, the team completes a sprint and delivers a potentially shippable product increment. However, the…

    2 条评论

社区洞察

其他会员也浏览了