CAPM Practice Exam Question

CAPM Practice Exam Question

In an Agile project, the team is conducting a sprint review meeting. Which of the following is the primary purpose of this meeting?

A) To identify and discuss process improvements for the next sprint

B) To showcase the work completed during the sprint to stakeholders and gather feedback

C) To estimate the effort required for the next sprint’s user stories

D) To assign tasks to team members for the upcoming sprint


Looking for more practice exam questions like this? Enroll in our online CAPM Exam Prep course, featuring more than 1,700 practice questions. By doing so, you can supercharge your CAPM Exam preparation and earn 37 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!


Best Answer: B) To showcase the work completed during the sprint to stakeholders and gather feedback

Explanation:

  • B) To showcase the work completed during the sprint to stakeholders and gather feedback is the correct answer because the primary purpose of a sprint review meeting in Agile is to demonstrate the potentially shippable product increment that the team has developed during the sprint. This meeting allows stakeholders to see the progress made, provide feedback, and collaborate on what to do next. It’s a critical part of the Agile process, as it ensures that the product evolves with regular input from stakeholders, keeping the project aligned with their expectations and needs.
  • A) To identify and discuss process improvements for the next sprint is incorrect because this activity occurs during the sprint retrospective, not the sprint review. The sprint retrospective is specifically aimed at evaluating the team’s process and identifying ways to improve efficiency and effectiveness in future sprints.
  • C) To estimate the effort required for the next sprint’s user stories is incorrect because estimating effort for the next sprint’s work is typically done during sprint planning, not during the sprint review. Sprint planning is where the team discusses and estimates the effort required for the upcoming sprint’s user stories, setting the stage for the work to be completed in the next sprint.
  • D) To assign tasks to team members for the upcoming sprint is incorrect because task assignment is usually a part of sprint planning or is handled collaboratively by the team during the sprint. Agile teams often prefer self-organization, where team members choose tasks based on their skills and availability rather than having tasks assigned to them.

In summary, the sprint review’s main objective is to demonstrate the completed work to stakeholders and gather their feedback. This ensures the project remains aligned with stakeholder expectations and that any necessary adjustments can be made early. The other options describe activities that are part of different Agile ceremonies, such as the sprint retrospective or sprint planning, making them incorrect in this context.


Maryanne Reilly

Skilled and Experienced IT, Healthcare, Medical Consultant

6 个月

B

回复
Muthukumar J S CSM

Certified Scrum Master | Project Management Professional | Business Analytics Consultant | Six Sigma Specialist | Yoga Instructor cum therapist | Passionate Astrologer

6 个月

Option B

回复
Bungsu Sinabutar

Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New

6 个月

Answer is B

回复

要查看或添加评论,请登录

Sabri C.的更多文章

  • PMP Practice Exam Question

    PMP Practice Exam Question

    In a project, the team identifies a risk that a critical feature may not be fully developed within the sprint due to…

    7 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the planning phase of a project, you identify a potential risk of a critical supplier failing to deliver on…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are in the process of closing a project and have received feedback from key stakeholders that certain deliverables…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a team meeting, a conflict arises between two team members, and one of them becomes visibly upset and starts…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the initial stages of a project, your team agrees on a set of ground rules to guide behavior and communication…

    1 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    As a project manager practicing servant leadership, how would you handle a situation where a team member is struggling…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are leading a newly formed project team and notice that team members are unsure about their roles and how their…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a project status meeting, two key team members begin arguing about the best approach to complete a task. Their…

    3 条评论
  • Agile Projects: Redefining How We Build the Future

    Agile Projects: Redefining How We Build the Future

    In a world where change reigns supreme, Agile project management emerges as a transformative approach that embraces…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    During a project, the team completes a sprint and delivers a potentially shippable product increment. However, the…

    2 条评论

社区洞察

其他会员也浏览了