In an Agile project, the team is conducting a sprint review meeting. Which of the following is the primary purpose of this meeting?
A) To identify and discuss process improvements for the next sprint
B) To showcase the work completed during the sprint to stakeholders and gather feedback
C) To estimate the effort required for the next sprint’s user stories
D) To assign tasks to team members for the upcoming sprint
Looking for more practice exam questions like this? Enroll in our online CAPM Exam Prep course, featuring more than 1,700 practice questions. By doing so, you can supercharge your CAPM Exam preparation and earn 37 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!
Best Answer: B) To showcase the work completed during the sprint to stakeholders and gather feedback
- B) To showcase the work completed during the sprint to stakeholders and gather feedback is the correct answer because the primary purpose of a sprint review meeting in Agile is to demonstrate the potentially shippable product increment that the team has developed during the sprint. This meeting allows stakeholders to see the progress made, provide feedback, and collaborate on what to do next. It’s a critical part of the Agile process, as it ensures that the product evolves with regular input from stakeholders, keeping the project aligned with their expectations and needs.
- A) To identify and discuss process improvements for the next sprint is incorrect because this activity occurs during the sprint retrospective, not the sprint review. The sprint retrospective is specifically aimed at evaluating the team’s process and identifying ways to improve efficiency and effectiveness in future sprints.
- C) To estimate the effort required for the next sprint’s user stories is incorrect because estimating effort for the next sprint’s work is typically done during sprint planning, not during the sprint review. Sprint planning is where the team discusses and estimates the effort required for the upcoming sprint’s user stories, setting the stage for the work to be completed in the next sprint.
- D) To assign tasks to team members for the upcoming sprint is incorrect because task assignment is usually a part of sprint planning or is handled collaboratively by the team during the sprint. Agile teams often prefer self-organization, where team members choose tasks based on their skills and availability rather than having tasks assigned to them.
In summary, the sprint review’s main objective is to demonstrate the completed work to stakeholders and gather their feedback. This ensures the project remains aligned with stakeholder expectations and that any necessary adjustments can be made early. The other options describe activities that are part of different Agile ceremonies, such as the sprint retrospective or sprint planning, making them incorrect in this context.
Skilled and Experienced IT, Healthcare, Medical Consultant
6 个月B
Certified Scrum Master | Project Management Professional | Business Analytics Consultant | Six Sigma Specialist | Yoga Instructor cum therapist | Passionate Astrologer
6 个月Option B
Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New
6 个月Answer is B