Can EOT be granted after the completion date?

Can EOT be granted after the completion date?

#ConstructionLaw101

Recently, someone sent me a screenshot asking the question above. I'm not ChatGPT, but since someone asked, let's try to give an answer based on what we know. First, we need to read what the contract says.

In clause 23.10 of PAM 2018, it's pretty specific and straightforward, stating:

“The Architect may within twelve (12) Weeks after the date of Practical Completion review and fix a Completion Date later than that previously fixed…”

While some contract clauses are clear about when the Contract Administrator should grant an Extension of Time (EOT), others are a bit vague. For example, clause 43.1 of PWD203A (Rev.1/2010) isn't specific about when EOT can be given:

“….then the SO may if he is of the opinion that the extension of time should be granted, so soon as he is able to estimate the length of the delay beyond the date or time aforesaid issue a Certificate of Delay and Extension of Time giving a fair reasonable extension of time for completion of the Works.”

In the past, there have been discussions about when EOT should be granted in contracts that aren't explicitly stated. A contract clause in the Miller v. London County Council (1934) case stated:

“It shall be lawful for the Engineer, if he thinks fit, to grant from time to time, and at any time or times, by writing under his hand such extension of time for completion of the work and that either prospectively or retrospectively and to assign such other time or times for completion as to him may seem reasonable.”

However, the court was strict and didn't allow the Engineer to grant EOT after the completion date, citing that the phrase 'either prospectively or retrospectively' didn't grant the Engineer the power to give EOT after the completion date.

In the subsequent case of Amalgamated Building Contractors Ltd v. Waltham Holy Cross Urban District Council (1952), the contract stated, “the Architect shall make a fair and reasonable extension of time for completion of the works”. It sounded similar to PWD203A, right? Hahaha…

The contractor argued that the clause meant the architect should provide a future completion date for the contractor, not a date that has already passed. Lord Denning, the judge, disagreed with the contractor. He said that practically, considering it from a business perspective, the architect should be able to give EOT even retrospectively (meaning after the completion date) – as in that case, since delays could arise until the last minute of completion, the architect must be able to grant EOT after completion. So, Lord Denning differed from the Miller case before that.

But Lord Denning also mentioned (more or less), in principle, there's a difference if the delay is caused by the contract administrator or owner, like being slow to provide the site or issuing variation orders, and so on. When such things happen, the Contract Time might cease to bind the contractor because the contract administrator or owner can't claim their 'right' in the contract if they themselves have faults causing the contract terms (i.e., completion on time) to be impossible for the contractor to fulfil. Therefore, EOT after the completion date can only be granted for delays due to neutral events beyond the control of the contract administrator or owner.

YA Lim Chong Fong discusses this extensively in his book, so go check it out.


Reference:

[1] PWD 203A (Rev-1/2010)

[2] PAM 2018 (With Quantities)

[3] Sundra Rajoo, Dato' W.S.W. Davidson, Ir. Harbans Singh K.S., “The PAM 2006 Standard Form of Building Contract”, 2010

[4] YA Lim Chong Fong, Malaysian PWD Form Of Construction Contract 2nd Ed, 2011

[5] Roger Knowles. 200 Contractual Problems and their Solutions. 3rd Edition, 2012

[6] Notes from Sr Johar Bahar, KAS Jurukur Bahan Perak. Can't remember when he gave it to me.

[7] Amalgamated Building Contractors Ltd v. Waltham Holy Cross Urban District Council (1952) – capaian di https://vlex.co.uk/vid/amalgamated-building-contractors-ltd-793872629



Tizazu Yibeltal

Field Engineer at government enterprise

5 个月

the discussions are good. But I have a question that`s not mentioned so far above. That is, my contractor claimed for EOT before a year with calendar 874 days. While we allowed only 450 days. And he`d accepted and went for action then. today the contractor submitted the second EOT request by incorporating some EOT events for the second time already that had been responded during his first time EOT requests. is it possible. Sincerely,

赞
回复

For somebody who has no experience in this field, shouldn't EOT be accorded before the end of completion date?

赞
回复
赞
回复
Muhamad Azad Ahmad Dinar

Civil Engineer, Asset Management, Construction, Project Management & QAQC

1 å¹´

Well written and good info ????

Ts. Mohd Rafis Mohamed, MBA, CMILT

Procurement and Contract Manager at PETRONAS | MBA | Chartered Member CILT | MBOT Panel Accreditation and Technologist Assessor | HRD Corp-TTT Certified Trainer |

1 å¹´

Thank you for sharing this useful article regarding PAM 2018 and PWD 203A

赞
回复

要查看或添加评论,请登录

Mazuan Lin的更多文章

  • SEHELAI GARIS HALUS PADA CONDITIONAL PAYMENT DI BAWAH CIPAA

    SEHELAI GARIS HALUS PADA CONDITIONAL PAYMENT DI BAWAH CIPAA

    #ConstructionLaw101 Antara perubahan ketara yang dibawa oleh CIPAA ke alam bina negara ni adalah berkaitan dengan…

    6 条评论
  • ARKITEK DAN KONSPIRASI

    ARKITEK DAN KONSPIRASI

    #ConstructionLaw101 Korang tau tak tahun ni ada arkitek yang kena tarik masuk Mahkamah Rayuan sebab dituduh…

    6 条评论
  • LOSS AND EXPENSE – MAAF KONTRAKTOR, BERITA BURUK.

    LOSS AND EXPENSE – MAAF KONTRAKTOR, BERITA BURUK.

    #ConstructionLaw101 Saya pernah menulis mengenai keputusan High Court (HC) yang membenarkan bayaran sebahagian dari…

    4 条评论
  • BOLEHKAH ARAHAN VO DIBERIKAN SELEPAS CNC YAKNI SEMASA TEMPOH LAD? JIKA BOLEH, BAGAIMANA EOT DIKIRA?

    BOLEHKAH ARAHAN VO DIBERIKAN SELEPAS CNC YAKNI SEMASA TEMPOH LAD? JIKA BOLEH, BAGAIMANA EOT DIKIRA?

    #ConstructionLaw101 Saya percaya ramai antara konsultan dan SO yang takut nak keluarkan apa-apa arahan VO selepas…

    3 条评论
  • PAYMENT OF LOSS AND EXPENSE BASED ON RECURRING ITEMS IN THE PRELIMS?

    PAYMENT OF LOSS AND EXPENSE BASED ON RECURRING ITEMS IN THE PRELIMS?

    #ConstructionLaw101 There are several points raised in Sunissa Sdn Bhd v Kerajaan Malaysia (2020), but there are two…

    5 条评论
  • COVID-19 - BOLEH CLAIM EOT TAK?

    COVID-19 - BOLEH CLAIM EOT TAK?

    Untuk mengelakkan Covid-19 dari terus merebak, kerajaan telah memutuskan untuk melaksanakan Perintah Kawalan Pergerakan…

    9 条评论
  • LAD: Past, Present, and Future in Malaysia

    LAD: Past, Present, and Future in Malaysia

    Introduction Liquidated and Ascertained Damages or LAD is a pre-established monetary sum for each day of the…

  • LAD: Mungkinkah ada sinar buat Employer?

    LAD: Mungkinkah ada sinar buat Employer?

    Bagi yang mengikuti perkembangan kontrak binaan, mungkin sudah sedia maklum bahawa selama 24 tahun kebelakangan ini…

    1 条评论
  • ADA GUNA KE KONTRAKTOR RESERVE HIS RIGHT UNTUK EOT & L&E?

    ADA GUNA KE KONTRAKTOR RESERVE HIS RIGHT UNTUK EOT & L&E?

    #ConstructionLaw101 Hari ni aku nak bagitau satu benda yang mungkin bernilai ribu-ribu atau juta-juta lemon (baca:…

    8 条评论
  • AKU, MAMAT DAN TERMINATION CLAUSE

    AKU, MAMAT DAN TERMINATION CLAUSE

    Mamat ni watsap saya beberapa hari lepas. Walaupun wording di dalam clause 25.

社区洞察

其他会员也浏览了