On the 20th July the government issued the first draft of the Building Safety Bill. The Bill responds to the independent review of building regulations and fire safety carried out by Dame Judith Hackitt following the Grenfell Tower disaster.

Dame Judith’s report made over 50 recommendations. The government have subsequently accepted all the recommendations and principles which have informed the bill.

There was a consultation paper, so we had a good idea as to what was going to be in the bill.

It has taken a few days to get my head around the information. There are 8 documents on the .gov website relating to the bill.

Firstly, there isn’t anything we didn’t expect, however there is a little more detail in some places. It is also different seeing something written as a bill rather than a report; it becomes very real.

Much of the detail as to how the law will be implemented is not included. Instead the bill sets out the jurisdiction of the regulator who will be the Building Safety Regulator to sit within the Health and Safety Executive.

What this means is even when the bill is passed there is still work to do.

I won’t go through the bill in detail, I will leave this to the lawyers. However, I have picked out some of the key points plus a few of the things which caught my eye.

The new Building Safety Regulator has three functions:

  •  Implementing the new, more stringent regulatory regime for higher risk buildings.
  • Overseeing the safety and performance of all buildings.
  • Assisting and encouraging competence among the built environment industry and those registered.

The regulator will maintain committees to advise on building functions including:

  • Building Advisory Committee.
  • Committee on industry competence.
  • Residents panel.

The legislation will encompass higher risk buildings. These buildings will be defined by the regulator.

When buildings are designed, constructed, or refurbished, those involved will have formal responsibilities. These will align with the CDM 2015 regulations to include:

  • Client
  • Principle designer
  • Principle contractor
  • Designer
  • Contractor

There is a new set of gateways for projects:

  • Gateway 1: Planning granted
  • Gateway 2: Construction work beginning
  • Gateway 3: Completion and Final Certificate

Golden Thread: The bill includes provisions that will help create a Golden Thread of information. The intention of the clauses in the bill is to ensure that the right people have the right information at the right time to ensure buildings are safe and building safety risks are managed throughout the building life cycle.

This information will be held digitally and will ensure that the original design intent and any subsequent changes to the building are captured, preserved, and used to support safety improvements

For new builds, the duty-holders must start to collect this information during the design and construction process.

Once construction is complete, the information must be handed over to the accountable person.

The Accountable Person: The accountable person is the duty-holder during occupation and is responsible for registering the building and applying for a building insurance certificate.

Once a building is registered the accountable person must also apply to the Building Safety Regulator for a Building Assurance Certificate. The Building Safety Regulator will issue a Building Assurance Certificate if it is satisfied that the accountable person is complying with meeting the statutory obligations placed on them.

Existing buildings that are already occupied will also need to be registered and existing buildings which are unoccupied at the introduction of the new regime will have to be registered by the point the building is occupied.

The accountable person must appoint a Building Safety Manager who must have the organisational capability and relevant skills knowledge experience and behaviours.

The role of the Building Safety Manager:

  • Comply with statutory duties as set out in the Bill
  • Managing the building in accordance with the safety case report for the building and ensuring that the requirements of the building assurance certificate are complied with
  • Keeping informed and cooperating with the managing agents of the building about safety measures and works
  • Complying with all directions given and statutory notices issued by the Building Safety Regulator
  • Cooperating with other occupiers or owners of the building

The safety case report: This is the document that goes to the Building Safety Regulator to make the claim of an argument for residents’ safety. It is essentially the response to the exam question “Can you identify the building safety risks in your building and show me how you manage these on an ongoing basis as far as you can so that it is safe?”

The safety case report summarises all the key components of the safety case with references to supporting documentation. It is supported by the wider safety case which refers to the totality of the building safety information and includes all the evidence that supports how these building safety risks are being managed and contained within the Golden Thread of information.

The accountable person must develop a strong partnership between residents and the Building Safety Manager. These obligations cover engagement and participation, complaints handling, information provision and the role of residents in helping to keep the building safe.

One such obligation is to produce and keep up to date a residence engagement strategy setting out how the obligations will be delivered in practice.

Building Control: The bill includes provisions to improve competence levels and accountability in the building control sector by creating a unified professional and regulatory structure for building control, changing, and modernising the existing legislative framework.

The role of a registered building inspector is being introduced. A registered building inspector is an individual who will be able to provide advice to local authorities or registered building control approvers overseeing building work.

The bill also removes the ability for a person carrying out any building work for higher risk buildings to choose their own building control body.

Construction Materials: The bill creates the concept of a safety critical product an gives the Secretary of State the power to make regulations to place safety critical products on a statutory list

Architects: The bill introduces a power for the Architects Registration Board to monitor competence of the architects.

Higher Risk Buildings: At the start of the new regulatory regime higher risk building will be formally defined as:

Two or more dwellings  

Two or more rooms for residential purpose

Student accommodation

 Where:

 The height is 18 metres or more above ground level ignoring any Storey which is a roof top plant and machine area or any storey consisting exclusively of plant and machinery

or

The building contains more than six storeys ignoring any storey which is below ground level

 And

 Room for residential purposes means a room other than in a dwelling which is used by one or more persons to live and sleep but excluding a room in

A residential care home

Secure residential institution Search as prison detention centre

Temporary accommodation Eg hotel hostel guest house hospital Hospice

 The Secretary of State can allow the Building Safety Regulator to charge fees and recover charges from those it regulates in relation to its functions.

It would appear existing occupied buildings will be transitioned into the new regime.

The building safety manager must report information related to the safety of an occupied building to the building safety regulator in a manner prescribed by the Secretary of State

The accountable person must establish and operate a system that will enable reportable information to be given to the building safety manager. This system will be assessed as part of the building assurance certificate application.

New information and reports required as part of the Bill:

Golden Thread of Information

Fire on structural safety building information held digitally to specific standards. These standards will include requirements around robust information management and keeping the information up to date. The Golden thread will ensure that those responsible for the building have the required information to manage building safety during throughout the lifestyle life cycle of the building

Building Assurance certificate

This certificate that an accountable person must apply for and the building safety regulator will provide if it is satisfied that the accountable person is complying with meeting the statutory obligations placed on them.

Gateway one, two and three

Three key stages in the building development where the duty holder must demonstrate that they are managing building safety risks appropriately before they are permitted by the relevant regulator to continue to the next stage of development.

Safety Case Report

A structured argument supported by a body of evidence that provides a compelling, comprehensive, evidenced and valid case as to how the accountable person is proactively managing fire and structural risks in order to prevent a major incident and limit the consequences to people in and around the building

New Roles included in the Bill:

Accountable Person

The accountable person is responsible for meeting the statutory obligations for occupied higher risk buildings, they will either be the building owner or have a repairing obligation of any part of the common areas of the building.

Management bodies are defined as the accountable persons in circumstances where the lease sets out repair and maintenance obligations on that management company.

Common parts include the structure and exterior of the building and any part of the building which is provided for the use of the residents in the building.

Building Safety Manager

Named by the accountable person, the building safety manager will support the accountable person by carrying out the day to day functions of ensuring that the building safety is safely managed and promote the openness trust and collaboration with residents that is fundamental to keeping buildings safe.

The Building Safety Regulator

The building safety regulator will be set up within the health and safety executive and make buildings safer through the implementation and enforcement of the new more stringent regulatory regime for buildings in scope stronger.

Oversight of the safety and performance of all buildings and assisting and encouraging competence among the built environment industry and registered building inspectors.

Registered Building Control Approved Inspector

Formally known as an approved inspector or a building control body under the old regulatory system. Refers to private sector firms doing building control work.

Registered Building Inspector

Refers to individual inspectors that are registered by the building safety regulator.

Timescales:

It is difficult to be specific regarding timescales. The bill needs to go through three readings in both the House of Commons and House of Lords, then amendments before it gets to Royal Assent. Typically, a Bill takes about a year to get through Parliament, however it may be this Bill moves quickly as there has been public criticism of the delays to date. Once the act has been passed there is likely to be a transitional period for the regulator to put processes pin place. On this basis I would anticipate building owners need to ha

Guy F.

Providing commercial property building surveying services, including facade remediation, major loss, expert witness, pathology, acquisition and technical due diligence consultancy.

4 年

Really useful summary Rob many thanks

回复
Edward Murphy

Founder, Ollio - The Building Performance Consultancy - making buildings the best they can be for users.

4 年

Great piece Rob. Reading it I got a bit of a concern that while everyone will get all excited about it at first, overtime it could revert to the same old, same old ways. We need root and branch change of approach to how we all do business in our industry. Then maybe some of this will stick, not because we are legally compelled to, but because it makes good ethical affordable business sense for all of us to do the right thing right.

Malcolm Shiels MSc CFIOSH

Health and Safety Manager, Galliford Try

4 年

When you read it Rob, you need to be watching the grenfell enquiry and you go "ah thats why they are doing that". Really useful summary Rob, if we (the industry) dont grasp this, dont look to use digitilisation, technology, and truly collaborate, then we should be ashamed, cheers

Lynda Thompson

Lynda with a Why ?? Relentlessly curious ?? The research I do for organisations informs change in #construction #fuelpoverty and #climate. Both freelance and part time employed.

4 年

Really, really helpful. Thanks for taking the time to review it in so much detail Rob Charlton

John Nielsen

Director at CK21 Ltd

4 年

Excellent summation Rob. As an industry we need to step up to the mark and take responsibility. We must all be aware.

要查看或添加评论,请登录

Rob Charlton的更多文章

  • Building Safety Act: Happy 3rd Birthday

    Building Safety Act: Happy 3rd Birthday

    Can you believe that on the 28th of April, it is 3 years since the Building Safety Act received Royal assent and became…

    1 条评论
  • Bimstore V5: We've come a long way...

    Bimstore V5: We've come a long way...

    Every few years, we give Bimstore a complete rebuild. Why? As the number of users and components grows, we need to…

  • Practice what we preach

    Practice what we preach

    After the lockdown and the shift in how we work, it became clear that our workspace was no longer fit for purpose - I'm…

    4 条评论
  • A unashamed pitch for Twinview

    A unashamed pitch for Twinview

    While typically, I don't use my blog to promote Space Group products or services, after reading Peter Apes's book…

  • Too good not to share

    Too good not to share

    I recently read the Proposed Construction Product Competence Standard White Paper published by the Construction…

    1 条评论
  • Principal Designer Confusion

    Principal Designer Confusion

    In the last few weeks, I’ve had numerous discussions surrounding the role of the Principal Designer, sparked by the…

  • The Concrete Scandal: A Call for Sustainable Building Practices and Accountability.

    The Concrete Scandal: A Call for Sustainable Building Practices and Accountability.

    Recently, the spotlight has been squarely fixed on the construction industry, accused of being one of the culprits…

    9 条评论
  • Does architecture inspire you?

    Does architecture inspire you?

    It's coming up to 30 years since I qualified as an architect, and I have never been more inspired by a building or a…

  • Does architecture inspire you?

    Does architecture inspire you?

    It's coming up to 30 years since I qualified as an architect, and I have never been more inspired by a building or a…

    1 条评论
  • The subtle difference between a Building Safety Case, a Safety Case Report and a Golden Thread.

    The subtle difference between a Building Safety Case, a Safety Case Report and a Golden Thread.

    It is approaching six years since the Grenfell Tower Disaster and 12 months since the Building Safety Act 2022 received…

    3 条评论

社区洞察

其他会员也浏览了