Building a Risk-Tolerant Schedule
Glen Alleman MSSM
Veteran, Applying Systems Engineering Principles, Processes & Practices to Increase the Probability of Program Success for Complex Systems in Aerospace & Defense, Enterprise IT, and Process and Safety Industries
Technical and programmatic disruptions in project plans don’t need to negatively impact cost, performance, or schedule metrics.?However, traditional planning approaches are not an adequate defense. This white paper outlines the six steps for building a risk-tolerant schedule using a field-proven approach.
In two prior white papers in this risk management series — “Risk/Opportunity” and “Managing Schedule Risk” — the importance of planning risk management tasks and managing different types of uncertainty in the project schedule was presented. This approach lays the foundation for building a risk-tolerant project schedule that identifies programmatic risk and implements the needed mitigation activities.
This issue presents a method for incorporating schedule risk management in a visible manner that provides governance of the project’s technical and programmatic performance. This method is based on three core concepts shared by all risk–tolerant plans:
Risk Management Structure
This chart describes the Risk Management structure
To build a risk-tolerant schedule, the PMBOK 3rd Edition instructs us to:
While this approach appears well grounded since it defines processes that can be used to build the schedule, it fails to address the core weakness of most planning processes by not being specifically designed to be Risk Tolerant in four ways:
Measurable Maturity and Embedded Risk Management
Building a Risk-Tolerant schedule starts with understanding that the traditional approaches to planning described above leave out the elements needed for risk tolerance. These elements begin with identifying and assessing the project, product, and process states as part of the schedule.
Steps in Building a Risk-Tolerant Plan
Define the measurable maturity of the project events. These assessment points can be determined based on the capabilities or fidelity of the deliverables agreed upon by the customer. Capabilities describe a defined outcome that is not the conclusion but lays the groundwork for continued value delivery.?[2] Objectives are reached, and the operational value is delivered when a defined capability is available. Features and functions describe the static and dynamic behaviors of a system. Still, they are not directly connected to a strategy, mission or vision defined in the chartering session of the project. Milestones indicate the arrival of a point in time. Capabilities delivery answers the question: to achieve the objective of this project, what capabilities must be possessed?
Define the Significant Accomplishments and the Exit Criteria that deliver the needed capabilities for the project. A capability is defined for each point along the maturity line – from immature to complete. Each Significant Accomplishment and its Exit Criteria needs to be worded as a past tense statement about the delivery of an end item. This delivery must be 100% of some defined result. No percentage complete is allowed! Instead, 100% of a partially defined capability, product, or service clearly states what “done” looks like at each place along the way to the completion of the project.
Define the work needed to deliver the Significant Accomplishments and their Exit Criteria. This focuses on defining what “done” looks like for each exit criterion. These tasks should represent the vast majority of the activities in the plan. Any 1.???? other work should be classified as Level of Effort.
Rank each task according to an ordinal risk scale. Each task must be ranked since it is unclear in the beginning which tasks will be critical to the completion of the schedule and which will interact and cause programmatic risks to appear.
The ranking of risk. Six basic classes are commonly used. [3] The probability scales commonly used are un-calibrated in most instances. These types of scales (un-calibrated) generally produce poor results unless the process is well structured, stable and repeatable.
Define alternative paths through the schedule for unknown risks, which are risks with a probability of occurrence but an unknown impact. The plan indicates these paths as branching probabilities.
领英推荐
The result is a plan where risks and their mitigations are visible, with risk ranking for each task delivering results for each Exit Criteria.
Increasing the Probability of Program Success
Cost and Schedule growth for any project or program is created when there are:
1. 1. Impractical technical performance expectations,
2. Impractical cost and schedule estimates,
3. Insufficient risk assessments, and
4. Unexpected technical challenges.
These are all based on poorly performed and ineffective risk management. These primary causes contribute to the program's technical and programmatic shortfalls. The table below shows the causes and their contributing factors that reduce the probability of program success, documented in various sources.
The Root Causes of cost and schedule growth and technical shortfall start with:
Processes and Practices
"Risk monitoring is the process that systematically tracks and evaluates the performance of risk–handling actions against established metrics throughout the project and develops further risk–handling options, as appropriate. It feeds information into the other risk management activities of planning, assessment, and handling." [5]?
If monitoring is passive, then it is just a bookkeeping function. Proactive risk monitoring provides quantitative information to decision-makers through variance in the Cost, Performance, Schedule, and changes in the risk analysis data. Earned Value provides cardinal values for Cost and Schedule (C-S) metrics. Technical Performance Measures provide cardinal values for Performance (P) metrics. The C-P-S cardinal values are the basis of a continuous risk management process by aligning risk reduction tasks with Significant Accomplishments and their Exit Criteria.
These risk monitoring metrics adjust the risk handling strategy and the Risk Handling Plan and provide information to update the risk probability and consequence portion of the risk analysis.
Learning to create a risk-tolerant schedule and managing the technical and programmatic risks this schedule represents is a practice. A high technology program manager once noted, "You can't learn surgery from reading a book — you need to complete a surgical residency."?
No amount of attending seminars or reading books or articles (even these articles) will provide the solution to managing schedule risks. But there are two good starting points: Risk Management Guide for DoD Acquisition, Fifth Edition (Version 2.0), Department of Defense, Defense Acquisition University, June 2003, and Effective Risk Management: Some Keys to Success, Edmund H. Conrow, AIAA Press, 2003.
These are recommended practicum guides. PMBOK?, while introductory, does not provide an integrated approach to Cost, Performance, and Schedule risk management.?
Other texts that should be on the shelf of any competent risk management professional include:
Bibliography