Bradley University Business and Engineering Complex Update - June 2018

Bradley University Business and Engineering Complex Update - June 2018

There will not be a summer break for the Business and Engineering Complex construction project. Although there has been a substantial amount of rain lately and intense heat, the construction activities continue to progress.

During the past 30 days, mechanical, electrical and plumbing work have continued in the basement level. Structural steel, metal decking and concrete flooring have been poured on the east side of the second floor of the building. Additional behind the scenes activity includes the delivery and rough-in of two large chillers, housed in the Renaissance Coliseum, that will be utilized for cooling needs. 

During the next 30, days we will continue to see the installation of structural steel which will rise above Burgess Hall. Steel stud installation will start on the lower levels of the east half of the building. Installation of the new steam and chilled water piping system will begin underground on the south side of the building, as well as the installation of new storm and sanitary piping on the west side of the building.  

Don't forget to check the webcam to see the progress at https://www.bradley.edu/webcams/complex/

???????? ????????

?????? ??????? ????? ?? ???????? ????????? ????????

6 年

??? ???? ?? ??? ?????? ?????? ????? ??????

  • 该图片无替代文字
回复
Ricardo Brito Martins

Planejamento, gest?o e execu??o de obras de constru??o civil

6 年

Very Good This construction! I like of estrutura metalic.

回复

要查看或添加评论,请登录

Renee Charles的更多文章

社区洞察

其他会员也浏览了