BILL OF QUANTITIES
Part 1

BILL OF QUANTITIES Part 1

Embarking on a construction project—from renovating your current house to building a new one--can be a stressful and daunting experience. You can feel overwhelmed with unknowns, risks, new terminology and details you may never have considered. The fear of construction costs exceeding one's budget is very real, but there is a professional tool available that will help even the layman throughout the duration of the project.

The bill of quantities ('BoQ') is a document prepared by a quantity surveyor that provides a clear, detailed description and measured quantities (number, area, volume, weight or time) of all the construction work and materials required to implement the architect's plans and specifications. 

The BoQ saves the cost and time of all the bidding contractors separately measuring the same drawings. Instead all the tenderers calculate their prices (including sub-contractors and optional works) based on the exact same quantities of the exact same components, so the BoQ provides a fair and transparent basis to solicit competitive bids. This helps avoid any guesswork, ambiguities or misunderstandings, and so prevents disputes arising from different interpretations of what has been priced.                                   

As opposed to the single price contract with minimal breakdown which affords considerable commercial advantage to the contractor, the playing field is now leveled, with offers that can only be submitted using the BoQ. Comparing the prices of not only the total job but also the individual items, allows a detailed assessment of which aspects of each bid offer good or poor value. This information will inform negotiations on both the micro and macro level.

 

Dorit Halfon

Provides headhunting services for S-UP & Tech Companies. Specializing in Executive and Technology positions. ??Looking for top .NET Fullstack Engineers for amazing opportunities in Ramat Hachyal, Tel Aviv ??"

4 年

Great for sharing

回复
Chananya Drucker

Motion Control Sales Manager at Conlog Ltd.

4 年

Loved the article, helps understanding the big picture. Thanks for sharing

回复
Guy ??? Rahamim

Voted 2022 & 2023 Top 100 CS Strategist | Helping R&D Teams to Unlock Business Outcomes | Senior Manager, Customer Success at LinearB | Founding Lead at CS Insider | CS Angel Member | CCSMP | MBA

4 年

Helpful! This great to know! Steven Drucker

回复
Eyal Avidov

CEO of Global Tech ? HLS | Defense | Automotive | Connecting StartUps & Fortune. Ask about our ????-??-???? Solutions (Biz Dev as A Service)

4 年

Thanks for sharing

Sapir Passler

Head Hunter | Recruitment Specialist | AI-Driven Sourcing Expert | Career Development Consultant & Lecturer | IDF 2 TECH Manager

4 年

Thank you so much for sharing ??????

要查看或添加评论,请登录

Steven Drucker的更多文章

  • BILL OF QUANTITIES, Part 2

    BILL OF QUANTITIES, Part 2

    Before construction begins and even before signing a contract, the BoQ can form a reliable basis for the project…

    1 条评论

社区洞察

其他会员也浏览了