Best Practices for Conducting a Schedule Risk Analysis (SRA)
Dayananthan Sivalingam PMP?, PMI-RMP?
Lead Engineer - Planning & Project Controls | Risk Analyst | Forensic Schedule Analyst |17 years | Oil & Gas | EPC
A Schedule Risk Analysis (SRA) is a critical tool in project management, providing insights into potential delays and helping to establish a robust plan to mitigate risks. Here’s a comprehensive checklist to ensure a thorough and effective SRA.
Purpose and Objectives
The primary goals of conducting an SRA are to:
- Determine the likelihood of program completion by the target date.
- Identify the amount of schedule risk contingency needed for acceptable certainty.
- Pinpoint risks most likely to delay the project.
- Identify paths or activities most likely to delay the program.
Pre-Simulation Assessment
Before running simulations, ensure the schedule is robust:
- Verify the schedule against best practices.
- Ensure the schedule network clearly identifies work and relationships between activities.
- Minimize and justify any date constraints in the schedule.
Duration Data Fields
For accuracy, include:
-Optimistic, most likely, and pessimistic duration estimates in your schedule.
Correlation and Uncertainty
It’s essential to:
- Account for correlations in the uncertainty of activity durations to get a realistic risk assessment.
Risk Prioritization
Focus on the most significant risks by:
- Prioritizing risks based on probability and magnitude of their impact.
Risk Register Utilization
Before conducting the SRA:
- Use the risk register to identify discrete risks.
Documentation
领英推荐
To maintain clarity and reproducibility:
- Ensure SRA data and methodology are available and well-documented.
Critical Path Identification
During the simulation:
- Identify activities that frequently appear on the critical path to closely monitor near-critical path activities.
Risk Input Validation
To ensure reliability:
- Validate risk inputs to ensure probabilities and impact ranges are reasonable.
- Confirm information is gathered from knowledgeable sources and free of bias.
Schedule Contingency
Prepare for uncertainties by:
- Including schedule contingency in the baseline schedule to account for risks.
- Calculating contingency by comparing the schedule date with the simulation result at a preferred certainty level.
Contingency Management
Effective management includes:
- Program manager holding and allocating schedule contingency to relevant parties as needed.
- Documenting the derivation and amount of contingency set aside for risk mitigation and unforeseen problems.
- Assessing schedule risk periodically to ensure contingency sufficiency.
Contractor Involvement
When working with contractors:
- Require contractors to perform an SRA during the formulation of the performance measurement baseline.
- Ensure the contractor’s schedule reserve is based on a preferred confidence level.
Periodic Updates
Keep the schedule relevant by:
- Performing an SRA periodically to update the schedule based on actual progress, updated activity durations and sequences, and new risks.
By following these best practices, project managers can significantly enhance their ability to predict and manage potential delays, ensuring projects are completed on time and within budget. Regularly updating and validating the SRA ensures that the project remains on track, even as new risks and challenges arise.