This process flow will help you to understand basic SCM-PP-EWM process flow from business point of view.
- All Production Planning master data (Material Master, BOM, Work Centre, Routing and Production Versions) are maintained correctly.
- All EWM master data are maintained correctly, like (Product Master /SCWM/MAT1, Controle Cycle LPK1 etc.)
Planning Process (Production Planner)
- Business enters forecast (MD61) or with any mass upload tool.
- Verify uploaded forecast (MD63) or directly in Stock Req. List (MD04).
- Execute MRP run (MD02) or MRP Live (MD01N).
- After MRP, for in-house (E) produced part system generates Planned Orders. Business can verify it in MD04 or Production Order Information System (COOIS).
- Perform ATP for planned order (MDVP) and Capacity Planning (CM01/CM21).
- Convert Planned Order to Production Order (CO40/CO41) or directly from Stock Req. List (MD04).
- Release Production Order (CO02) or Mass Release (CO05N), after release and save, system performs printing, PMR for EWM etc.
SCM-EWM Process (Warehouse Manager & Warehouse Operator)
- Once, production order is released, system generated Production Material Request (PMR) for EWM system, warehouse business verifies the PMR with transaction /SCWM/PMR.
- Against the PMR, business performs material staging with transaction /SCWM/STAGE, which generates warehouse task in EWM.
- Once business, confirms these warehouse task (/SCWM/MON), requested components are staged at PSA maintained in the Production Work Centre.
Production Process (Production Supervisor & Production Operator)
- Production user performs order confirmation (CO15 or CO11N).
- If Backflush is enabled for components, system automatically posts GI (261) while performing CO11N, else business posts GI manually via MIGO.
- Once GI is posted from ERP, an outbound delivery (OBD) gets created in ERP and it gets distributed in EWM system.
- If auto-GR is enabled, system automatically posts Goods Receipt (101) at the order confirmation (CO15/CO11N), else business posts GR manually via MIGO.
PP-EWM Process (Warehouse Manager & Warehouse Operator)
- Once, outbound delivery is distributed to EWM system, business process the outbound delivery via /SCWM/PRDO or directly in Warehouse Monitor /SCWM/MON.
- Once, inbound delivery is distributed to EWM system, business process the inbound delivery via /SCWM/PRDI or directly in Warehouse Monitor /SCWM/MON.
- In case any error occurs during processing of GI/GR from EWM system, it gets captured in EWM Queues (Transaction SMQ2), business can access is directly from Warehouse Monitor /SCWM/MON.
- Upon successful posting of GI/GR from EWM system, corresponding Inbound or Outbound Delivery gets completed in ERP system and material document posted in ERP system for the same.
Production Process (Production Supervisor & Production Operator) - TECO
- Upon successful confirmation of orders, business verifies that all the operations are confirmed correctly and GI/GR posted via Production Order Information System (COOIS).
- Now, Production orders are marked technically closed (TECO), via transaction CO02 or mass processing tool COHV.
SAP PP PPDS Senior Consultant
1 年Dear Aditya, your article is a perfect example, how to present such a complex stuff like SCM-PP-EWM integration in 10 minutes. BR
Well Done ??
Expert PP/PPDS Consultant SAP
1 年Woa
SAP MM & S4 HANA Sourcing & Procurement Certified Consultant
1 年Very good ??
Senior SAP Consultant (PP / Lead QM) at Goldfish IT GmbH
1 年Great job...the article gives very clear process flow. Keep it up