Ban These Planning Abominations

Ban These Planning Abominations

In 2009 I posted this article on Planning Planet, it caused a bitter controversy then but it is still applicable today, I called it:

Ban these planning abominations.

This is the code according to Mike Testro.

The only true critical path is developed by a Finnish start link between activities, all other adaptations are wrong.

Every activity should represent one trade in one location, anything longer than 10 days is too long.

Use bottom-up planning to form programme levels:

level 4 - individual task

level 3 - task summary showing geographical location.

level 2 – Zone or Section of work

level 1 - Project.

Never ever use;

Lead Lag Links either + or -

start start and/or finish finish links

start – finish links - ever.

Mid Chart Links

Start – Stop Constraint flags

ALAP positioning

any task with no successor links.

Any of the above abominations will combine to distort the true critical path.

Why did the software suppliers still allow these abominations in the systems?

True planners everywhere, join me in my crusade to ban these abominations.

Mike Testro 16 January 2009.

Anyone disagree today?

Jeremy Fearnsides

Owner @ Fearnsides and Associates - Construction Management Services Consultants - Claims, Delay Analysis, Commercial, Contract Admin & Management, Project Controls, QS & Expert Witness(delay, quantum & support).

2 年

Better still, ignore the logic

回复

要查看或添加评论,请登录

Mike Testro的更多文章

  • KEY Milestones

    KEY Milestones

    Key Milestones to use when planning. Multi Storey Structures 1 Introduction.

    5 条评论
  • Collapsed Critical

    Collapsed Critical

    Collapsed Critical An Alternative to TIA 1 The fundamental difference. 1.

    7 条评论
  • Prolongation Costs Explained

    Prolongation Costs Explained

    Prolongation costs? Delay analysts and quantum experts often discuss the topic of prolongation costs after an extension…

    4 条评论
  • Offer - Acceptance - Consideration

    Offer - Acceptance - Consideration

    Fred and Bill were best mates. Scenario 1 Fred noticed that there was a shop in town with a computer that he…

    7 条评论
  • Collapsed Critical

    Collapsed Critical

    A simple method of analysing delays using every relevant event. Note: this method only works using ASTA PowerProject 1…

    2 条评论
  • Certificate of Competence

    Certificate of Competence

    Of the many candidates that have subscribed to and studied my 10 modules on the Basic Principles of Delay Analysis…

  • Entitlement - Need - Calculate

    Entitlement - Need - Calculate

    Comparisons of meaning of three different forms of contract. 1 Extensions of time.

  • A solution to the EOT problem.

    A solution to the EOT problem.

    Currently Main Contractors compete mainly on price. The biggest risk that all parties face is delayed completion.

    4 条评论
  • Snakes & Ladders - M&E Interface With The Structrure

    Snakes & Ladders - M&E Interface With The Structrure

    Mechanical & Electrical Work (M&E) 0. Overview 0.

    4 条评论
  • Basic principles of prolongation costs.

    Basic principles of prolongation costs.

    1 Basic principles of prolongation costs. 1.

    5 条评论

社区洞察

其他会员也浏览了