ANRE estimates that only 10-15 % of RES projects reach completion

ANRE estimates that only 10-15 % of RES projects reach completion

Chairman of the National Energy Regulatory Authority (ANRE) Claudiu Dumbraveanu said that, of the total number of renewable energy projects that have obtained the network connection approval, only 10-15 % will be realized.

According to Dumbraveanu, at the moment, 878 connection approvals have been issued for wind and solar projects. However, the number of projects with connection approval that also have signed network connection contracts concluded within the deadline stipulated by the legislation is much smaller - 365.?Finally, the number of projects with the authorization for the establishment of energy capacities issued by ANRE is only 77, with a total installed capacity of 1,445 MW.?

Thus, projects with a combined capacity of only 611 MW will be put into operation nationwide this year.

However, there will be a peak next year, with capacities amounting to 1,881 MW being put in operation.?In Romania, 3,026 MW in wind and 1,638 MW in solar are currently in operation, excluding prosumers.


Access our Energy News service on Balkan Energy Power

Portal: www.portal.balkanenergy.com


Balkan Energy AG is a leading provider of short and long term Power price forecasts, analytics, energy news and info for Hungary and SEE region. In addition to our well known services, we have recently implemented an extensive "10-year price forecast for HUPX and SEE markets (2025-2035)"

要查看或添加评论,请登录

社区洞察

其他会员也浏览了