In this project JWI continued to support our pharmaceutical client who needed a 700kg Chiller lifting to the second floor plantroom. The limited access for plant and equipment severely limited the choice of ways to carry out this project. We used a Unic 376 in the airlock to undertake this job which was very tight to set up in the small space with the limited head room. It was essential that it was professionally planned and supervised by our Technical Manager. Our client was "over the moon" at the professionalism of the job.
Factory Maintenance Manager
4 年Great work! A really neat piece of kit you’re using there!
Managing Director @ Jack Waghorn International Ltd | Hi-Tech Machinery installation, Lifting Ops & Project Planning
4 年Well done to our team involved in this project