The manufacturing process for 4680 batteries involves several precise and specialized steps to ensure the production of high-quality, high-performance cells. These cylindrical cells, known for their larger size and enhanced energy density, follow a meticulous assembly process. Here’s a comprehensive look at each stage in the 4680 battery manufacturing line:

1. Cell Core Material Preparation

The process begins with the receipt of the cell's core material, known as the "卷芯" (wound core). This core is the foundation of the battery and consists of the anode, cathode, and separator materials wound together to form the cell’s internal structure.

2. Positive Electrode Tab Welding

In the next step, the positive electrode current collector is welded. This process involves attaching the positive electrode tabs to the current collector, which is essential for establishing electrical connections within the cell. The welding must be precise to ensure optimal electrical conductivity and mechanical stability.

3. Negative Electrode Tab Welding, Hi-Pot Testing, and Tab Folding

The negative electrode current collector is then welded, followed by Hi-Pot (High Potential) testing. The Hi-Pot test checks the insulation between the electrode and the cell casing to ensure there are no leaks or short circuits. After welding and testing, the negative electrode tabs are folded to prepare them for the next assembly steps.

4. Negative Electrode End Coating

The negative electrode ends are coated with a protective layer. This coating process helps to safeguard the electrode from environmental factors and enhances the cell's overall durability and performance.


5. Bottom Cap Marking

The bottom cap of the cell is marked with identifying information. This marking is crucial for tracking and quality control throughout the manufacturing process.

6. Bottom Cap Welding and Current Collector Bonding

The bottom cap is then welded to the positive electrode current collector, and the components are bound together. This welding ensures a secure connection and proper alignment of the cell's components.

7. Casing Assembly and Bottom Sealing

The cell is then placed into its casing, followed by the bottom sealing weld. This step involves enclosing the cell in its outer shell and sealing the bottom to protect the internal components and ensure structural integrity.

8. Top Cover Welding

The top cover of the cell is welded in place. This process is essential for sealing the cell and providing protection against leakage and contamination. The welding must be precise to ensure a strong and reliable seal.

Laser welding

9. Final Steps: Tab Folding, Cover Assembly, Sealing, Hi-Pot Testing, and Nitrogen Leak Testing

The final steps include folding the electrode tabs, assembling the top cover, and sealing the cell. After these steps, the cell undergoes another round of Hi-Pot testing to confirm the integrity of the insulation. Additionally, a nitrogen leak test is performed to ensure there are no leaks in the sealed cell, providing an extra layer of quality assurance.

------------------------------------------------------------------------------

Overall, the manufacturing process for 4680 batteries involves a series of detailed and carefully controlled steps. From the initial core material preparation to final testing and sealing, each stage is crucial for producing cells that meet high standards of performance and safety. This meticulous approach ensures that the 4680 batteries are reliable, durable, and ready for use in advanced applications such as electric vehicles.