Accurate Work Order Close Out
Ricky Smith CMRP, CMRT, CRL
VP World Class Maintenance Maintenance and Reliability Advisor/ Educator, Book Author
"Accurate Work Order Close Out is important for the continuous improvement of any Maintenance Organization / Asset Reliability."
The objective of accurate data collection is to assist management in making the right decisions at the right time and to empower workers to make decisions at the floor level.
Work Orders are NOT:
Work Orders are used as a…
General Rules of Work Orders
Work Orders should have at the minimum the correct code:
Without the above information one cannot determine:?
Repair or Corrective Work orders should have the information as stated above everything as stated above plus, component code, failure code, and cause code if an organization wants to mitigate unexpected failures.
Without the right information on work orders when closed one cannot determine:
Dominant Failure Thread – which component has the most specific failure modes with a specific cause across multiple assets.
Dominant Failure Pattern – which failure pattern is the most dominant and what are the major causes of failures for this pattern. This allows one to develop strategies to eliminate unacceptable failures which impact the organization.
Establish the Criteria for WO Order Priority (all work orders are not equal).
See chart below to illustrate work order priority levels, time to respond, consequence of delaying the work, and likelihood of failure.
领英推荐
Preventive Maintenance/Predictive Maintenance Work Orders should…
Example: (failure mode – how something fails, example: Lack of Lubrication)?
On a PM Procedure it should have specific steps and specifications on what is to be done to known best practices.?
Example: Lubricate Bearing –
Step 1: Clean the grease fitting.?
Step 2: Clean the end of the grease gun to ensure no contamination will be introduced into the bearing.?
Step 3: Insert 4 grams of lithium grease (two shots)?
When closing all Work Orders the following items should be included:
Define Roles and Responsibilities for the effective use of Work Orders using the RACI Model (see RACI Example Below)
Perform RCA when WOs that do not meet expectations.?
"The 5 Whys may Provide the Root Cause"
Join me at one of my upcoming workshops at: https://worldclassmaintenance.org/maintenance-workshops
Planificación / Gestión de Activos / Confiabilidad
2 年Hello Ricky, as always, your posts are "always timely". But I can't believe that We (as maintainers) have not been able to sell the importance of "data quality" if you have read some of my posts, I insist on data quality as the base of the pyramid, there is no good or bad ERP. bad if we do not include good data, and those responsible for that are the maintenance engineers and after them the planners... Quality OTs are basic to improve the response of Coorective work and to improve our PM... Greetings from Costa Rica... #Backtotheroots #Reliability #Confiabilidad #Plantaconfiable
Asset Management, Reliability Engineering, Project Management and Maintenance Planning Expert - Specialist.
2 年Sometimes you need to backtrack over the road you have traveled in order to reset the direction to an intentionally better destination. If you haven’t kept diligent records of your journey you have nothing to calibrate against to prevent repeating the same miss steps to a unknown destination. If people don’t understand something they don’t value it and if they don’t value it they see no logic in allocating time and resources to it. Educating everyone in the broader maintenance team on why it is critical to capture 100% of the data associated with a repair/maintenance events enables everyone to work more efficiently.
Engineering Line Lead
2 年Accuracy of data contained within work orders is crucial to the success of any CMMS system. I have seen examples of work orders that contain incorrect information, which has lead management off on the wrong tangent when trying to determine root cause. I bang the drum continually to my team to ensure that work orders are accurate, contain the correct detail and are closed out in a timely manner. Work orders really are the support framework for the entire engineering function.
Reliability Leadership - Asset Management, RAM(S) Engineering, Maintenance, RCM / FMECA, ERP/EAM, Reliability, FTA, RCFA. KTP Supervision.
2 年Absolutely, this is so important. Finishing this aspect enables others to do their job.