20 Key Steps for Creating an Effective Project Time Schedule.
Introduction:
Project scheduling is a critical component of successful project management, this article will guide you through the steps of creating a project schedule, starting from the Bill of Quantities (BOQ) and contract, and ending with the Baseline (BL) schedule. Let's dive into the process.
1.????? Project Initialization:
2.????? Reviewing the Contract:
According to the F I D IC Red Book (1999 Edition), Clause 8.3 titled "Programme for the Works," the Contractor is required to submit a detailed time schedule within 28 days after receiving the Engineer's Notice to Commence.
3.????? ?Define Work Breakdown Structure (WBS):
4.????? Creating Activity List:
Based on the drawings, BOQ, and contract requirements, create a comprehensive list of project activities in an Excel sheet to be used in upcoming steps.
4.1.?????Construction activities,
Read well the BOQ Most of the mentioned items are possible to split into more than one activity, such as (concrete work for columns) you will find as one item, but it’s preferred to split it into Formwork, steel fixing, pouring, and curing to get more control over the project.
4.2.?????Engineering activities,
You should request from the technical office team a list/package of drawings that will prepared for the project with its trade and the sequence of submission to the Engineer (Architecture, Electrical, Civil, and Mechanical) to fit with the schedule.
4.3.? Procurement activities,
From BOQ, define the items that will need to be delivered to the site from the local/global market and prepare activities for it such as (Delivery to site steel fixing, Masonry, Wires, Pumps, etc.
5.????? Resources Availability Assessment:
Now after defining the activity list, you know what resources are required.
6.????? Define Production rates:
?Production rates are typically measured in units of work completed per unit of time (e.g., cubic meters of concrete poured per hour /day, linear meters of pipe installed per day).
7.????? Estimating Durations:
7.1.???? Construction Activities:
Ensure that your duration estimates are realistic and achievable.
?
7.2.???? Engineering Activities:
7.3.???? Procurements Activities:
8.??? Set Up Calendars:
? Working days are essential for determining task durations. Common working days in construction projects in Egypt for example from Saturdays to Thursdays.
The hours within a working day when project work can proceed. Common working hours are typically 8:00 AM to 5:00 PM.
? such as weekends and public holidays.
?In some projects, multiple shifts might be employed. Each shift has its working hours and rest days.
Multiple calendars may be necessary to better align with the specific conditions of the project, such as a calendar tailored for sub-contractors, suppliers, specific resources, etc.
9.??? Project Team Sessions:
Now we have most of the required data to create the schedule, but before proceeding we should prepare a session with the project team (Project manager, technical office manager, construction manager, etc.)
10.? Sequencing Activities:
Sequencing activities is a critical step when preparing a time schedule for a project. Here are the key steps for establishing the sequence of activities in a time schedule:
领英推荐
11.? Scheduling:
After completing the previous steps and creating the activities and the relationships in Primavera P6 software, Primavera will use the critical path method to calculate the forward and backward paths.
?Primavera P6 will provide you with planned start and finish dates for all project activities. You will also have access to information such as total project duration, early start and finish dates, late start and finish dates, and float (slack) for non-critical activities
?The output of the scheduling process in Primavera P6 is a detailed project schedule that includes a timeline, showing when each activity is planned to start and finish. You will also have a clear view of the critical path activities and milestones.
12.? Verify the scheduled dates:
In this step, check if the project’s finish dates/milestones of the project fit the contractual dates.
1.?????? Review Contractual Agreements:
reviewed the project's contractual agreements, statement of work (SOW), and any other relevant documents. Mentioned on the specified milestones, deadlines, and completion dates outlined in the contract.
?Identify any variances between the contractual dates and the project schedule. These variances could include tasks or milestones that are behind, ahead of schedule, or not aligned with the contract at all.
?Assess the impact of schedule variances on the overall project timeline. Determine if any delays or changes in milestone dates will affect the project's successful completion and its compliance with contractual obligations.
If it is determined that the project schedule doesn’t align with contractual dates, you may need to adjust. Depending on the nature and severity of the variances, this could involve (Revising Task Dependencies and reallocating Resources.)
13.? Assigning Resources:
?Before assigning resources, it's essential to assess the availability of resources as clarified in point 5
?You can create a table in Excel where the columns represent project activities, and the rows represent available resources. This table will help you organize and assign resources more easily.
??Assigning resources with the budget units for different categories (material, labor, and non-labor) Each activity should have a clear allocation of budget units
?You can utilize the import and export features of Primavera to streamline the resource assignment process:
a.?????? Export Excel Sheet:
You can export resource assignment sheets from Primavera to Excel.
b.?????? Import Excel Sheet:
You can import the Excel sheet containing resources again after assigning the resources.
14.? Resource levelling:
15.? Checking the Critical Path:
?Any delay in these activities will directly impact the project's completion date so we need to make sure of the health of the path.
16.? Define Cost Breakdown:
17.? Cost Loading:
where you allocate or "load" the budgeted costs to individual tasks or activities in your project schedule. This allows you to track and manage the financial aspects of your project, ensuring that costs are distributed appropriately across various project components.
18.? Verify the Funding limit reconciliation:
Ensuring that the value of the work falls within the financial constraints
19.? Review and Adjust:
Carefully review the initial schedule and make necessary adjustments to align it with project constraints and objectives. This may involve resource leveling, resolving conflicts, or revising activity sequences.
20.? Display and Printing:
Conclusion:
?Creating a project schedule is a structured and iterative process that involves careful planning, resource allocation, and continuous monitoring. Starting from the BOQ and contract, and culminating in the Baseline Schedule, this comprehensive approach helps you manage complex projects effectively and achieve project success. Mastering Primavera P6's features empowers project planners to streamline their scheduling processes and deliver projects on time and within budget, while also keeping a close eye on the critical path to ensure project success.
MSc.(Const.Mgmt.)Hons., BSc.(Civil.Eng.), (MCIOB-Charter Construction Manager), (PMP), (CM-LEAN) ,(MEngNZ)
1 年Great stuff! Thanks for posting.