The 10 "Musts" to Implement Earned Value Management on all Projects

Successfully applying Earned Value Management to projects requires 10 processes

  1. Define Work Scope
  2. Create an Integrated Bottom-Up Plan
  3. Formally Schedule Control Account Plan(s)
  4. Assign Each CAP to an Executive for Performance
  5. Establish a Baseline that Summarizes CAPs
  6. Measure Performance Against Schedule
  7. Measure Cost Efficiency Against the Costs Incurred
  8. Forecast Final Costs Based on Performance
  9. Manage Remaining Work
  10. Manage Baseline Changes
  11. Conclusion

1. Define the Work Scope

You must define 100 percent of the project's work scope using a work breakdown structure (WBS). Perhaps the most critical and most challenging requisite to employing earned value is to define the project's total work scope. This is a difficult task for any project, and particularly so for software projects. Yet, if you do not define what constitutes 100 percent of the assumed work, how can you measure the project's performance in a definitive way? Without a 100 percent reference point, how can anyone ascertain whether you have completed 10 percent, 20 percent, or 25 percent of a job? Realistically, no one can define a new job with absolute precision, but you must make some intelligent assumptions about a new project to quantify the work with sufficient confidence that the defined effort can be planned, scheduled, and estimated with some degree of certainty.

Anything less, and management must commit to a job by authorizing a "blank check" for the project. How does one define a job when specific details are often lacking? There are no absolute answers, but one of the most useful of all tools available to any project manager is the WBS. The WBS is to the project manager what the organization chart is to the executive-it allows the project manager to define a new endeavor by laying out all the assumed work, then decomposing each task into measurable work packages. Once the WBS is assumed to constitute a reasonable portrayal of the new project, it can be used to take the next steps in the project planning process, including the make-or-buy analysis, risk assessment, planning, scheduling, estimating, and authorization to proceed.

2. Create an Integrated Bottom-Up Plan

You must combine critical processes, including defined work scope, schedule, and estimated resources, into an integrated bottom-up plan of detailed measurement cells called Control Account Plans (CAPs). Earned value project management is implemented within detailed CAPs, which therefore constitute formal bottom-up project planning. The individual CAPs represent the integration of all critical processes such as work scope, planning, scheduling, estimating, and authorization. The performance measurement will take place within the detailed CAPs, and the total project's performance is the summation of what was reflected in the detailed CAPs. In essence, each project CAP is a subproject of the total project that is managed, measured, and controlled by a CAP manager.

3. Formally Schedule CAPs

Each of the defined CAPs must be planned and scheduled with a formal scheduling system. This is perhaps the single most critical tool required to implement earned value. The project's scheduling system will portray the approved work scope, which is carefully placed into a specific timeframe for performance. In earned-value vernacular, this scheduled work will constitute the project's planned value. As performance takes place on the project, the portion of the planned value that is physically accomplished becomes the earned value. Both the planned value and the resulting earned value must use the same metrics to measure their performance. The project's scheduling system is, therefore, critical to the employment of earned value because it is the vehicle to represent the project's scope, planned value, and earned-value measurement. The project master schedule is vital to the project because it constitutes the project manager's specified planned value for everyone to follow.

4. Assign Each CAP to an Executive for Performance

Each of the defined CAPs must be assigned to a permanent functional executive for performance. This assignment effectively commits the executive to oversee the performance of each CAP. Projects are by their nature transient within any firm's permanent organizational structure-they are authorized, implemented, and performed, then eventually go out of existence. Many (perhaps most) of those who manage the detailed performance that takes place within the CAPs will not carry the formal title of "manager" within the firm's permanent organizational structure; rather, many or most of these CAP managers are functional employees temporarily assigned and matrixed into the project by one of the permanent functional organizations. To secure a firm commitment from the functional executives who have the authority and resources to make the plan happen, it is wise to have each of the defined project CAPs essentially adopted by a senior function person with a title such as vice president, director, or manager.

5. Establish a Baseline that Summarizes CAPs

A total project performance measurement baseline must be established, which represents the summation of the detailed CAPs. The next required step is to form a total baseline against which project performance may be measured. Such baselines must include all defined CAPs plus any management (contingency) reserves that may be held by the project manager. If management reserves are not given to the project manager but are instead controlled by a senior management committee, they should be excluded from the project performance baseline. On a commercial-type contract, the baseline may include such things as indirect costs-and even profit or fee-to match the total authorized project funds. Internal projects will typically not contain indirect costs, profits, or management reserves. Most internal project baselines will be the sum of the defined CAPs.

6. Measure Performance Against Schedule

Periodically, you must measure the project's schedule performance against its planned master project schedule. The formally issued and controlled project master schedule constitutes the project's planned scope. Each task described on the project master schedule can be loaded with estimated resources, such as hours or dollars, which are embedded within the authorized CAPs. As performance takes place within the CAPs, you can quantify the relationship between the value of the work scheduled as compared to the value of the work accomplished. The difference between the work scheduled and work accomplished constitutes the schedule variance in earned value. A negative schedule variance means that the value of the work accomplished does not match the value of the work scheduled, i.e., the project is falling behind in its scheduled work. Each behind-schedule task can be assessed regarding its criticality to the project. If the late task is on the critical path, or if the task carries a high risk to the project, efforts can be made to get the late task back on schedule. Conversely, if a task has positive variance or is not considered a high risk to the project, added resources should not be spent to accelerate its performance.

7. Measure Cost Efficiency Against the Costs Incurred

You must periodically measure the project's cost performance efficiency rate, which represents the relationship between the project's earned value performed and the costs incurred to achieve the earned value. The single most important benefit of employing earned value is the cost-efficiency readings it provides. The difference between the value of work performed and the costs incurred to accomplish the work provides the cost-efficiency factor. If you are spending more on the project than it receives in value, this reflects an overrun condition. Absolute overruns have been found to be nonrecoverable. Overruns expressed as a percentage value have been found to deteriorate unless the project takes aggressive actions to mitigate the condition. Perhaps of greatest benefit, the cost efficiency rate has been found to be usably stable from the 15 percent point of project completion and progressively more stable as it goes from the 20 percent to 30 percent to 40 percent completion point. Therefore, the cost-efficiency factor is an important metric for any project manager or enterprise executive to monitor.

8. Forecast Final Costs Based on Performance

Periodically, you must forecast the project's final cost requirements based on its performance against the plan. One of the more beneficial aspects of the earned-value concept is its ability to independently forecast the total required funds at the end of a project, commonly called the "estimate at completion." Based on project performance against the plan, a project manager can accurately estimate the total funds required to finish the job within a finite range of values. These statistical estimates are something like a grass-roots sanity check against estimates based more on wishful thinking because they provide a more realistic estimate of the values needed to finish the job-unless someone has a preconceived notion of what that value should be. As reflected in Figure 1, if the earned-value statistical estimates are greater than the "official" project estimates to complete the project, someone in a senior management position should reconcile these professional differences of opinion.

9. Manage Remaining Work

You must continuously manage the project's remaining work. The results achieved to date on a project, good or bad, are in effect "sunk costs"-gone forever. Thus, any improvements in performance must come from future work tasks ahead of the latest status date. Earned value allows the project manager to accurately measure the cost and schedule performance achieved to date. If the results thus far are less than desired, the project manager can exert a more aggressive posture on all future work. Earned value, because it allows the project to quantify the value of its work achieved accurately, allows the project manager to also quantify the value of the work ahead to stay within the objectives set by management.

10. Manage Baseline Changes

You must continuously maintain the project's baseline by managing all changes to the baseline. The project performance measurement baseline you put in place at the start of the project is only as good as your management of all proposed changes to the baseline during the duration of the project. Any performance baseline quickly becomes invalid if you fail to incorporate changes into the approved baseline either by the addition to or elimination of added work scope. All new changes of project work must be addressed either by the approval or rejection of changes. For the initial baseline to remain valid, every change must be closely managed. Maintaining a baseline is as challenging as the initial definition of the project scope at the start of the project.

Conclusion

The earned value project management concept as a part of the more formal C/SCSC or EVMS has been demonstrated to be an effective technique in the management of major projects. Unfortunately, most of the experience with the concept has been restricted to those applications where the U.S. government has imposed the technique on major new systems acquisitions for which it retains the risk of cost growth.

However, the best opportunities for earned-value employment may well lie in the management of thousands of smaller projects that are being directed by people who may well be unaware of earned value. We believe the concept should be considered any time the risk of cost growth resides with a project manager, any time a lump sum or fixed price contract is used, and on all in-house funded developmental projects where a firm commitment is made to management. It should be considered any time a project manager could benefit from receiving an early warning cost signal in time to alter the ultimate direction of a project. Software projects can especially benefit from the employment of a simple earned-value approach.

Oliver F. Lehmann, MSc, ACE, PMP

Project Management Trainer, Project Business Trainer, Founder of the Project Business Foundation

2 年

Hi Glen, may I recommend two more? The two biggest reasons why EV brings no value? 1. Make sure that baselines are made from plans that are consistent and compliant. Inconsistent or non-compliant plans are products of phantasy. To compare a real project with a phantasy project will always be unfavorable for the real one. 2. Ensure consistency of data around the Data Date. See the image below. As people ignore the two errors shown, their data will be wrong. Managers (incl. project managers) love to make decisions based on numbers. Give them the wrong numbers, and they will make poor decisions.

  • 该图片无替代文字

要查看或添加评论,请登录

Glen Alleman MSSM的更多文章

  • Researching with AI (Part 2)

    Researching with AI (Part 2)

    The ChatGDP summarized the Origin and Adoption of the 49 Steps in Model and SimulationDevelopment. Origin and Adoption…

    1 条评论
  • Researching with AI (Part 1)

    Researching with AI (Part 1)

    I'm writing a book for Taylor & Francis on Deploying Digital Engineering Systems. One of the chapter sections is on the…

  • PM World Journal Articles

    PM World Journal Articles

    I'm collecting materials for a Digital Engineering Strategy implementation in Government and Commerical Domains. So…

    1 条评论
  • Quote of the Day

    Quote of the Day

    "Wealth breeds a class of people for whom human beings are disposable commodities. Colleagues, employees, kitchen…

  • An Interview

    An Interview

    An interview with Michael Clayton https://www.youtube.

    2 条评论
  • Quote of the Day

    Quote of the Day

    “As Americans, we should be frightened—deeply afraid for the future of the nation. When good men and women can’t speak…

    4 条评论
  • 3 - Workforce Plan for Deploying Digital Engineering

    3 - Workforce Plan for Deploying Digital Engineering

    Digital Engineering is a fundamental change to the way people work and operate. It incorporates digital computing…

    1 条评论
  • 2 - Fundamentals of Digital Engineering Systems

    2 - Fundamentals of Digital Engineering Systems

    This is the 2nd in a 3-part series on Digital Engineering. The 1st introduced the Capabilities of Digital Engineering.

  • Some GovLoop Publications

    Some GovLoop Publications

    GovLoop is The Knowledge Network for the Government of more than 300,000 federal, state, and local government peers in…

  • Five Immutable Principles of Project Success No Matter the Domain, Context, Management Tools, or Processes

    Five Immutable Principles of Project Success No Matter the Domain, Context, Management Tools, or Processes

    Here is a collection of materials I use to guide project success when we are not immune to common reasons for project…

    6 条评论

社区洞察

其他会员也浏览了