The #1 mistake planners make in Power BI

The #1 mistake planners make in Power BI

I tend to share a lot about the applications of Power BI in Project Control because it is truly amazing. It is something that I wished to have when I started my career a long time ago. Power BI can help planners provide immense value to their teams and help projects move forward. However, this tool can be fatal and useless if the user is not competent in using the software.

Although the charts look great on the surface, the results are often inaccurate and misleading. After speaking with many practitioners, I realized that their lack of data analytics knowledge is the most common reason why they fail to produce the results they intend to have in their projects.

No alt text provided for this image

In planning, the project schedule may consist of thousands of activities. Each activity has several attributes that include some of the following:

  • Activity ID
  • Activity Description
  • Original Duration
  • Budgeted Total Cost
  • Budgeted Labor Units
  • Activity Codes
  • Planned Early and Late Dates

Moreover, remarkable changes take place to many activities on this list on weekly basis. These changes include some of the following:

  • Schedule % and Activity % complete.
  • Variance %
  • Planned cost and planned labor units.
  • Earned value cost and earned value labor units.
  • Actual start/finish dates, if applicable
  • SPI
  • Remaining Cost
  • Total Float

We have now a HUGE set of data to deal with. We all know how to ask the right questions and how to get the right answers. The challenge is how long will it take you to do this? And can you always guarantee that you perfectly validated your calculations? The below approach includes some steps that planners follow to prepare?reports, answer questions, and analyze progress.

  • Import XER files
  • Have multiple excel sheets full of formulas (pivot tables if you are really good)
  • Browse hundreds of PDF reports to find the information they need.
  • Copy data from P6 to excel and walk their way through.
  • Always update manually (progress curves, indicators,?dashboards, progress matrix and reporting in general)
  • Set up multiple?P6?filters, copy data into excel, apply formulas to prepare?reports, and finally work on formatting.
  • Planners always hoped that the correct XER files were used, correct P6 filters were applied and accurate excel formulas were developed.

No alt text provided for this image

We need data analytics skills to manage this huge set of data, process information quicker and deliver results much faster. Data analytics is a specialization area where people pursue a whole career in. Yet, we as engineers haven’t learned anything about it in college or even deal with this area on daily basis at work. I signed up for FOUR different Power BI courses in the past. The most valuable training I received was delivered by a Microsoft Certified Data Analyst.?

I made a lot of mistakes and had sleepless nights to figure out what has gone wrong with my report until everything started to click with me. Planners have to be familiar with the below data analytics principles in order to deliver the expected results.

  • Data Normalization
  • Cardinality
  • Data Models
  • Cross Filter Direction
  • Snowflake Schemas
  • Primary and Foreign Keys

No alt text provided for this image

The above principles should be well understood by planners before they use Power BI. Otherwise, they will generate tons of misleading results and live an unnecessary nightmare.

The final common mistake engineers make is that they attempt to apply Power BI in planning while they are still complete beginners. In my opinion, it is the project control first, Power BI second. Beginners should fully understand the project control knowledge first (e.g. schedule network behaviors, earned value, SPI, progress curve) before they use Power BI. In Excel, you will see the data in front of you all the time. However, in Power BI, you don’t see the whole data in front of you unless you navigate to the data tables. Therefore, it is easy to make unintentional fatal mistakes in Power BI.

No alt text provided for this image

To sum up, there is an overwhelming huge set of data to manage in project planning and control. Planners should be familiar with the principles of data analytics before they start using Power BI. Moreover, beginners are advised to learn the concepts and methods of planning before they use Power BI.

Regards,

Osama Saad, MBA, PMP, PSP, CCP, PMI-SP

Douglas Bazo de Castro, MBA

Geologist | Mathematician | Database Technician | Project Manager | Scrum Master | Project Scope | Data Base Analyst | Master's Candidate Unicamp

1 年

Cool insight! I really enjoyed reading it.

Peter Holroyd

Nearly Retired at BROOKSON (5409) LIMITED

2 年

Why do you concentrate on P6? Most raw project data exists in other company systems of various quality, hertiage and software application from which the planner extracts the infornation he needs only some of it goes gets loaded into P6 but he uses all the information to plan the future work.

要查看或添加评论,请登录

Osama Saad, MBA, PMP, PSP, CCP, PMI-SP的更多文章

社区洞察

其他会员也浏览了