In April 2023, PES began work on a customer’s offshore, topside replacement four-pile deck. Most of the fabrication was completed in December 2023 when the team began assembly, lasting through April 2024. The team completed the loadout in May 2024. PES managed the procurement, prefabrication, final assembly, coatings, pressure testing and transportation onto a client-furnished barge. Although PES has successfully executed several refurbishment platforms, this 700-ton topside was the first new build for the company. Great job to #TeamPES and all involved!
-