On November 21, Sarah Haga and Purnima Samaroo from UPC and Oriana Cole from the NYC Department for the Aging to KCS for a site visit to review the progress of our kitchen renovation project. During the visit, we confirmed several key milestones: the demolition phase is now complete, HVAC equipment has been delivered on-site, and the underground plumbing rough-in has been successfully completed and passed inspection. Our guests enjoyed a productive tour of the site, highlighting the exciting transformations underway. We’re thrilled to see this project taking shape and are grateful for the support and collaboration making it all possible! From left: Sarah Haga/UPC, Myounmi Kim/KCS, Purnima Samaroo/UPC, Hyunil Kim(KCS) & Oriana Cole(NYC Department for the aging)
-
-
-
-
-