CSDEE Engineering Trenchless / Utilities is an Engineering Consulting business. CSDEE provides Design and Independent Verifier services for civil engineering infrastructure in particular Public Utility Plant in roadway and rail crossings. We are RIW registered as ARTC Civil Design Verifier/Approver and Major Construction Verification. We provide VicTrack Independent Compliance Reports for design including AS 4799 compliance. CSDEE provides CIPP and Pipe Relining systems Design to AS/NZS 2566.1 and Installation Certification for full length reline and point liner (patch repair) for 50-100 years design service life. Systems currently used for full length reline are Reline Europe Alphaliner, BKP Berolina-Liner, Impregliner, Saertex-Liner and Brawoliner. Point repair system used is Trelleborg epros?DrainPacker . CSDEE specialises in Public Utility Plant (PUP) including mapping to satisfy AS 5488 and design for relocations and new services including sewer, water, stormwater, gas, oil, telecomms and power. We undertake Dilapidation Survey, Condition Assessment and Remaining Useful Life Appraisal to inform design and rehabilitation options.
- 所属行业
- 土建工程
- 规模
- 2-10 人
- 总部
- Varsity Lakes,Queensland
- 类型
- 私人持股
- 创立
- 2005
- 领域
- Dilapidation Survey、Pipeline and Chamber Rehabilitation、Design Verification、Construction Certification、Safety in Design risk assessment、Public Utility Plant、Condition Assessment、CPEng、RPEQ、RIW、GRP structural pipe relining、GRP point liner certification、Water and Wastewater、Independent Verifier、ARTC and VicTrack、CIPP Design、Condition Assessment、AS 4799-2000、AS/NZS 2566.1和AS 5488-2013
地点
-
主要
4 Valbonne Avenue
AU,Queensland,Varsity Lakes,4227
CSDEE Engineering Trenchless / Utilities员工
动态
-
Trelleborg DrainPacker to the rescue again this week for DN375 FRC joint displacement repair. AquaDig completed the on-maintenance CCTV survey and asked for a suitable solution to the displaced joint which occurred when the upstream and downstream sections were joined in the middle due to access constraints on a 10% grade embankment. CSDEE solution was 3layer x 400mm wide first liner across the joint with 2layer 600mm wide second liner directly over the first. Displacement and exfiltration resolved!
-
-
CSDEE has recently been endorsed by Queensland Rail as External Engineering Organisation (EEO) and we are listed in the QR website on the Approved EEO Vendors page. Christopher Dee has achieved registration for Job Roles: QR - Construction Certifier and QR - Design Certifier. Rail Industry Worker (RIW) profile is shown below for ARTC and QR Job Roles for which he is currently registered. Please reach out to CSDEE in the event that you are needing our services for working within or adjacent these rail corridors.
-
-
CSDEE Engineering Trenchless / Utilities转发了
DN375 RCP circumferential crack repair with BluCem HE80 applied 2mm thickness by our client Pipe Spy using a robotic trowel within the installed pipe. This repair is based on BCC s160 Figure?3.2 – Repair Method A for cracks less than 0.5mm wide where autogenous healing is unlikely to be completed within the 12months on-maintenance period. Bond strength has been tested using 4000psi jetting which does not affect the repair after 28days curing. BluCem HE80 provides tensile and bond strength similar to the RCP and has 100year durability which matches the AS/NZS 4058:2007 requirements in 3.4.5 finishing and repairs for pipes. This crack repair method is accepted by most Councils in Southeast Queensland and Northern NSW.
-
-
DN375 RCP circumferential crack repair with BluCem HE80 applied 2mm thickness by our client Pipe Spy using a robotic trowel within the installed pipe. This repair is based on BCC s160 Figure?3.2 – Repair Method A for cracks less than 0.5mm wide where autogenous healing is unlikely to be completed within the 12months on-maintenance period. Bond strength has been tested using 4000psi jetting which does not affect the repair after 28days curing. BluCem HE80 provides tensile and bond strength similar to the RCP and has 100year durability which matches the AS/NZS 4058:2007 requirements in 3.4.5 finishing and repairs for pipes. This crack repair method is accepted by most Councils in Southeast Queensland and Northern NSW.
-
-
CSDEE have undertaken many condition assessments for 50-70 year old sewer pumpstations in need of rehabilitation and capacity upgrade. This design is a quantum leap forward using long life materials which will enable simple capacity upgrade with minimal downtime!
Yet another pretty sewer pump station recently designed, installed and commissioned for a residential subdivision, fully compliant with and handed over to the local water authority by QMax Pumping Systems. This one incorporated initial stage smaller internal riser pipework, for easy change over to ultimate stage at a later date. Experience the easy process and speak with the friendly team at QMax today for your upcoming development requiring a pump station. #qmaxpumpingsystems #sewerpumpstation #sewer #wastewater #precastconcrete #qmax
-
-
-
-
-